ITAC Assessment: KG0012
ITAC logo
ITAC Assessment: KG0012
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Bowling balls
NAICS
n/a
SIC 3949: Sporting and Athletic Goods, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 120,000
ft2
Annual Production 1,000,000
pieces
Production Hrs. Annual 2,184
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $228,798 3,927,902
kWh
Natural Gas $35,607 9,433
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $31,343 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $29,560

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7261: Install timers and/or thermostats $24,209 $3,300 $24,209
679,953
kWh
02 2.4133: Use most efficient type of electric motors $2,343 $14,260 $2,343
55,979
kWh
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,151 $2,099 $2,151
60,668
kWh
04 2.4221: Install compressor air intakes in coolest locations $1,135 $468 $1,135
15,826
kWh
05 2.6231: Utilize controls to operate equipment only when needed $857 $300 $857
24,326
kWh
06 2.4231: Reduce the pressure of compressed air to the minimum required $648 $20 $648
9,086
kWh
TOTAL RECOMMENDED $31,343 $20,447 $31,343
845,838
kWh
TOTAL IMPLEMENTED $29,560 $19,959 $29,560
820,926
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs