Assessment Year | 2016 |
---|---|
Principal Product | Metal Stamping |
NAICS | 332119: Metal Crown, Closure, and Other Metal Stamping (except Automotive) |
SIC | 3466: Crowns and Closures |
Sales Range | $10 M to 50M |
# of Employees | 66 |
Plant Area |
126,000
ft2
|
Annual Production | 58,140
pieces
|
Production Hrs. Annual | 2,168
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $122,181 | 1,347,500 |
kWh
|
$0.091 |
Electricity Demand | $21,288 | 8,064 |
kW-mo/yr
|
$2.64 |
Electricity Fees | $240 | - |
|
- |
Natural Gas | $37,458 | 6,719 |
MMBtu
|
$5.57 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,053 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $21,698 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,132 | $8 |
$975
10,758
kWh
|
$157
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,539 | $77 |
$1,539
16,969
kWh
|
- | - | - | |
03 | 2.7261: Install timers and/or thermostats | $2,844 | $181 |
$2,844
31,364
kWh
|
- | - | - | |
04 | 2.4322: Use or replace with energy efficient substitutes | $1,873 | $422 |
$1,873
20,663
kWh
|
- | - | - | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $2,760 | $93 |
$2,388
26,339
kWh
|
$372
-
kW-mo/yr
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $483 | $198 |
$416
4,591
kWh
|
$67
-
kW-mo/yr
|
- | - | |
07 | 3.4151: Minimize water usage | $9,506 | $6,223 |
$(-888.0)
(-9,792)
kWh
|
$(-365.0)
-
kW-mo/yr
|
$1,799
-
MMBtu
|
$8,960
-
Tgal
|
|
08 | 2.7135: Install occupancy sensors | $330 | $293 |
$330
3,642
kWh
|
- | - | - | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $826 | $840 |
$711
7,846
kWh
|
$115
-
kW-mo/yr
|
- | - | |
10 | 2.2511: Insulate bare equipment | $519 | $576 | - | - |
$519
-
MMBtu
|
- | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,693 | $11,326 |
$9,565
105,497
kWh
|
$128
-
kW-mo/yr
|
- | - | |
12 | 2.4221: Install compressor air intakes in coolest locations | $548 | $957 |
$472
5,209
kWh
|
$76
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $32,053 | $21,194 |
$20,225
223,086
kWh
|
$550
-
kW-mo/yr
|
$2,318
-
MMBtu
|
$8,960
-
Tgal
|
||
TOTAL IMPLEMENTED | $21,698 | $14,102 |
$20,783
229,236
kWh
|
$915
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs