Assessment Year | 2015 |
---|---|
Principal Product | Commercial Printing |
NAICS | 323111: Commercial Printing (except Screen and Books) |
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $10 M to 50M |
# of Employees | 105 |
Plant Area |
55,000
ft2
|
Annual Production | 1,000
lb
|
Production Hrs. Annual | 6,868
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $105,106 | 1,786,840 |
kWh
|
$0.059 |
Electricity Demand | $51,178 | 4,834 |
kW-mo/yr
|
$10.59 |
Electricity Fees | $1,646 | - |
|
- |
Natural Gas | $11,446 | 1,322 |
MMBtu
|
$8.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $43,173 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,448 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,690 | - |
$1,285
21,759
kWh
|
$404
-
kW-mo/yr
|
- | - | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $6,360 | - | - |
$6,360
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,057 | $167 |
$4,057
68,766
kWh
|
- | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $2,828 | $665 |
$2,474
41,939
kWh
|
$354
-
kW-mo/yr
|
- | - | |
05 | 2.7135: Install occupancy sensors | $10,659 | $801 |
$10,659
180,661
kWh
|
- | - | - | |
06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,713 | $310 | - | - | - |
$3,713
-
MMBtu
|
|
07 | 2.4234: Cool compressor air intake with heat exchanger | $1,476 | $340 | - | - | - |
$1,476
-
MMBtu
|
|
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,278 | $5,296 |
$3,647
61,813
kWh
|
$1,631
-
kW-mo/yr
|
- | - | |
09 | 2.253: Infiltration | $5,896 | $5,317 |
$5,896
99,924
kWh
|
- | - | - | |
10 | 2.3212: Optimize plant power factor | $1,104 | $5,400 | - | - | $1,104 | - | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $113 | $385 |
$113
1,922
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $43,173 | $18,680 |
$28,132
476,784
kWh
|
$8,749
-
kW-mo/yr
|
$1,104 |
$5,189
-
MMBtu
|
||
TOTAL IMPLEMENTED | $9,448 | $5,848 |
$7,818
132,501
kWh
|
$1,631
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs