ITAC Assessment: IC0182
ITAC logo
ITAC Assessment: IC0182
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Coating and Resins
NAICS 325211: Plastics Material and Resin Manufacturing
SIC 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers
Sales Range $10
M
to 50
M
# of Employees 32
Plant Area 102,732
ft2
Annual Production 25,000,000
lb
Production Hrs. Annual 5,832
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $169,074 3,364,284
kWh
Electricity Demand $69,058 6,348
kW-mo/yr
Natural Gas $299,840 52,435
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $37,901 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $75 $116 $16
315
kWh
$5
-
kW-mo/yr
- - $54
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,306 $672 $959
19,195
kWh
$961
-
kW-mo/yr
- - $386
03 2.7142: Utilize higher efficiency lamps and/or ballasts $273 - $137
2,716
kWh
$169
-
kW-mo/yr
- $(-33.0) -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $9,045 $43,859 $6,680
133,590
kWh
$1,991
-
kW-mo/yr
- - $374
05 2.4151: Develop a repair/replace policy $2,734 $11,001 $2,106
42,116
kWh
$628
-
kW-mo/yr
- - -
06 2.4133: Use most efficient type of electric motors $3,070 - $2,284
45,713
kWh
$786
-
kW-mo/yr
- - -
07 2.2136: Install / repair insulation on steam lines $4,314 $5,489 - - $4,314
-
MMBtu
- -
08 2.1233: Analyze flue gas for proper air/fuel ratio $950 $311 - - $950
-
MMBtu
- -
09 2.1113: Reduce combustion air flow to optimum $2,442 $311 - - $2,442
-
MMBtu
- -
10 2.1123: Install automatic stack damper $5,217 $50,324 - - $5,217
-
MMBtu
- -
11 2.4221: Install compressor air intakes in coolest locations $2,294 $921 $1,767
35,344
kWh
$527
-
kW-mo/yr
- - -
12 2.4323: Use optimum size and capacity equipment $1,314 $1,318 $1,314
26,280
kWh
- - - -
13 2.6242: Minimize operation of equipment maintained in standby condition $379 $379 $319
6,394
kWh
$60
-
kW-mo/yr
- - -
14 2.3212: Optimize plant power factor $3,378 $20,932 - $3,378
-
kW-mo/yr
- - -
15 2.6211: Conserve energy by efficient use of vending machines $110 - $85
1,700
kWh
$25
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $37,901 $135,633 $15,667
313,363
kWh
$8,530
-
kW-mo/yr
$12,923
-
MMBtu
$(-33.0) $814
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs