ITAC Assessment: IC0066
ITAC logo
ITAC Assessment: IC0066
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Plastic and Aluminum Containers
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 380
Plant Area 376,000
ft2
Annual Production 66,000,000
lb
Production Hrs. Annual 8,520
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,324,077 25,383,708
kWh
Electricity Demand $145,778 38,978
kW-mo/yr
Electricity Fees $4,354 -
Natural Gas $167,535 44,436
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $220,561 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.7135: Install occupancy sensors $5,571 $8,423 n/a $5,460
105,000
kWh
$111
-
kW-mo/yr
- -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $14,454 $19,501 n/a $13,282
255,427
kWh
$1,172
-
kW-mo/yr
- -
03 2.6231: Utilize controls to operate equipment only when needed $16,576 $2,920 n/a $16,166
310,887
kWh
$410
-
kW-mo/yr
- -
04 2.4322: Use or replace with energy efficient substitutes $43,869 $12,078 n/a $39,825
765,953
kWh
$4,044
-
kW-mo/yr
- -
05 2.6231: Utilize controls to operate equipment only when needed $13,337 $39,718 n/a $12,580
241,924
kWh
$757
-
kW-mo/yr
- -
06 2.6232: Install set-back timers $98,862 $75,187 n/a $71,940
1,383,266
kWh
$26,922
-
kW-mo/yr
- -
07 2.7261: Install timers and/or thermostats $1,972 $3,710 n/a - - $1,972
-
MMBtu
-
08 2.2437: Recover waste heat from equipment $7,849 $14,148 n/a $(-1,176.0)
(-22,628)
kWh
$(-242.0)
-
kW-mo/yr
$9,267
-
MMBtu
-
09 2.7243: Improve air circulation with destratification fans / other methods $18,071 $78,893 n/a $(-2,334.0)
(-44,878)
kWh
$(-480.0)
-
kW-mo/yr
$22,145
-
MMBtu
$(-1,260.0)
TOTAL RECOMMENDED $220,561 $254,578 $155,743
2,994,951
kWh
$32,694
-
kW-mo/yr
$33,384
-
MMBtu
$(-1,260.0)
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs