Assessment Year | 2015 |
---|---|
Principal Product | Stock tanks |
NAICS | 332439: Other Metal Container Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
150,000
ft2
|
Annual Production | 80,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $69,537 | 1,480,800 |
kWh
|
$0.047 |
Electricity Demand | $29,093 | 3,732 |
kW-mo/yr
|
$7.80 |
Electricity Fees | $1,052 | - |
|
- |
Natural Gas | $65,807 | 11,655 |
MMBtu
|
$5.65 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,411 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,411 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,361 | $6,263 |
$4,369
92,951
kWh
|
$992
-
kW-mo/yr
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $1,907 | $7,104 |
$990
21,065
kWh
|
$917
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,451 | $5,839 |
$1,451
30,865
kWh
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,230 | $463 |
$1,002
21,373
kWh
|
$228
-
kW-mo/yr
|
- | |
05 | 2.6214: Shut off pilots in standby equipment | $814 | $60 | - | - |
$814
-
MMBtu
|
|
06 | 2.4221: Install compressor air intakes in coolest locations | $419 | $539 |
$341
7,273
kWh
|
$78
-
kW-mo/yr
|
- | |
07 | 2.7447: Install vinyl strip / high speed / air curtain doors | $229 | $371 | - | - |
$229
-
MMBtu
|
|
TOTAL RECOMMENDED | $11,411 | $20,639 |
$8,153
173,527
kWh
|
$2,215
-
kW-mo/yr
|
$1,043
-
MMBtu
|
||
TOTAL IMPLEMENTED | $11,411 | $20,639 |
$8,153
173,527
kWh
|
$2,215
-
kW-mo/yr
|
$1,043
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs