| Assessment Year | 2017 |
|---|---|
| Principal Product | Munitions |
| NAICS | 332992: Small Arms Ammunition Manufacturing |
| SIC | 3482: Small Arms Ammunition |
| Sales Range | $50 M to 100M |
| # of Employees | 125 |
| Plant Area |
743,000
ft2
|
| Annual Production | 23,000,000
pieces
|
| Production Hrs. Annual | 2,079
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $318,528 | 5,618,462 |
kWh
|
$0.057 | |
| Electricity Demand | $126,502 | 20,811 |
kW-mo/yr
|
$6.08 | |
| Natural Gas | $254,258 | 46,383 |
MMBtu
|
$5.48 | |
| Waste Disposal Costs | |||||
| Water Usage | $13,414 | 9,582 |
Tgal
|
$1.40 | |
| Water Disposal | $25,530 | 3,908 |
Tgal
|
$6.53 | |
| TOTAL YEARLY COSTS | $738,232 | ||||
| RECOMMENDED SAVINGS* | $67,620 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $67,620 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $23,860 | $39,900 | - |
$23,860
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,030 | $41,200 |
$4,480
104,000
kWh
|
$6,550
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,870 | $3,000 |
$5,210
120,850
kWh
|
$5,660
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.2121: Increase amount of condensate returned | $10,870 | $19,400 | - | - |
$2,530
-
MMBtu
|
$870
-
Tgal
|
$7,470 | |
| 05 | 2.2511: Insulate bare equipment | $10,990 | $9,760 | - | - |
$10,990
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $67,620 | $113,260 |
$9,690
224,850
kWh
|
$36,070
-
kW-mo/yr
|
$13,520
-
MMBtu
|
$870
-
Tgal
|
$7,470 | ||
| TOTAL IMPLEMENTED | $67,620 | $113,260 |
$9,690
224,850
kWh
|
$36,070
-
kW-mo/yr
|
$13,520
-
MMBtu
|
$870
-
Tgal
|
$7,470 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs