ITAC Assessment: IA0327
ITAC logo
ITAC Assessment: IA0327
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Aluminum Die Castings
NAICS 331523: Nonferrous Metal Die-Casting Foundries
SIC 3363: Aluminum Die-Castings
Sales Range $10
M
to 50
M
# of Employees 265
Plant Area 110,000
ft2
Annual Production 4,000,000
ton
Production Hrs. Annual 6,240
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $466,239 15,053,708
kWh
Electricity Demand $213,957 28,416
kW-mo/yr
Natural Gas $381,149 87,950
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $149,795 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,566

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,481 $809 $5,651
142,708
kWh
$2,830
-
kW-mo/yr
- -
02 2.4221: Install compressor air intakes in coolest locations $10,028 $1,017 $6,767
170,906
kWh
$3,261
-
kW-mo/yr
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $2,928 $104 $1,952
49,296
kWh
$976
-
kW-mo/yr
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,965 $479 $1,310
33,072
kWh
$655
-
kW-mo/yr
- -
05 2.7135: Install occupancy sensors $596 $1,131 $596
14,994
kWh
- - -
06 2.4133: Use most efficient type of electric motors $994 $303 $497
12,548
kWh
$497
-
kW-mo/yr
- -
07 2.6231: Utilize controls to operate equipment only when needed $4,163 $500 - - $4,163
-
MMBtu
-
08 4.445: Install equipment to move product $120,640 $40,000 - - - $120,640
TOTAL RECOMMENDED $149,795 $44,343 $16,773
423,524
kWh
$8,219
-
kW-mo/yr
$4,163
-
MMBtu
$120,640
TOTAL IMPLEMENTED $16,566 $1,716 $8,100
204,552
kWh
$4,303
-
kW-mo/yr
$4,163
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs