Assessment Year | 2008 |
---|---|
Principal Product | Doors |
NAICS | 321911: Wood Window and Door Manufacturing |
SIC | 2431: Millwork |
Sales Range | $10 M to 50M |
# of Employees | 115 |
Plant Area |
200,000
ft2
|
Annual Production | 8,897
thousand feet
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $43,107 | 1,285,242 |
kWh
|
$0.034 |
Electricity Demand | $18,810 | 3,420 |
kW-mo/yr
|
$5.50 |
Electricity Fees | $2,435 | - |
|
- |
Natural Gas | $63,500 | 6,045 |
MMBtu
|
$10.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $81,297 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $42,837 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Other Energy Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.1192: Reduce scrap production | $34,537 | - | - | - | - | $34,537 | |
02 | 2.9114: Use solar heat to make electricty | $19,500 | $157,850 |
$19,500
2,000
kWh
|
- | - | - | |
03 | 2.6218: Turn off equipment when not in use | $8,560 | $3,680 | - | - |
$8,560
-
MMBtu
|
- | |
04 | 2.7135: Install occupancy sensors | $7,000 | $44,710 |
$7,000
244
kWh
|
- | - | - | |
05 | 2.2443: Re-use or recycle hot or cold process exhaust air | $8,300 | $2,500 |
$8,300
631
kWh
|
- | - | - | |
06 | 2.3212: Optimize plant power factor | $3,400 | $5,075 | - | $3,400 | - | - | |
TOTAL RECOMMENDED | $81,297 | $213,815 |
$34,800
2,875
kWh
|
$3,400 |
$8,560
-
MMBtu
|
$34,537 | ||
TOTAL IMPLEMENTED | $42,837 | $2,500 |
$8,300
631
kWh
|
- | - | $34,537 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Other Energy Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs