Assessment Year | 1999 |
---|---|
Principal Product | fluid milk |
NAICS |
n/a
|
SIC | 2026: Fluid Milk |
Sales Range | $10 M to 50M |
# of Employees | 135 |
Plant Area |
100,000
ft2
|
Annual Production | 17,100
Tgal
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $201,290 | 5,832,943 |
kWh
|
$0.035 |
Electricity Demand | $83,017 | 13,980 |
kW-mo/yr
|
$5.94 |
Natural Gas | $21,174 | 6,927 |
MMBtu
|
$3.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $44,836 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,381 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Water Consumption Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $9,832 | - |
$5,885
254,982
kWh
|
$3,947
-
kW-mo/yr
|
- | - | - | - | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $2,453 | $265 |
$1,330
57,737
kWh
|
$1,123
-
kW-mo/yr
|
- | - | - | - | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,066 | $25 |
$1,124
48,652
kWh
|
$942
-
kW-mo/yr
|
- | - | - | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $554 | $43 |
$301
13,189
kWh
|
$253
-
kW-mo/yr
|
- | - | - | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,522 | $9,183 |
$1,639
70,926
kWh
|
$1,883
-
kW-mo/yr
|
- | - | - | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,864 | - |
$2,438
70,926
kWh
|
$2,426
-
kW-mo/yr
|
- | - | - | - | - | - | |
07 | 2.7135: Install occupancy sensors | $453 | $665 |
$453
19,637
kWh
|
- | - | - | - | - | - | - | |
08 | 2.1213: Direct warmest air to combustion intake | $431 | $650 | - | - |
$431
-
MMBtu
|
- | - | - | - | - | |
09 | 3.4111: Use closed cycle process to minimize waste water production | $15,177 | $11,511 |
$(-1,260.0)
(-15,989)
kWh
|
$(-1,055.0)
-
kW-mo/yr
|
- |
$11,089
-
Tgal
|
- | - |
$6,403
-
Tgal
|
- | |
10 | 3.4156: Use flow control valves on equipment to optimize water use | $995 | $1,046 | - | - | - |
$631
-
Tgal
|
- | - | - | $364 | |
11 | 3.5217: Reuse / recycle/ sell paper products | $1,915 | $100 | - | - | - | - |
$1,735
-
lb
|
$180 | - | - | |
12 | 4.231: Purchase equipment instead of leasing | $2,574 | $3,900 | - | - | - | - | - | $2,574 | - | - | |
TOTAL RECOMMENDED | $44,836 | $27,388 |
$11,910
520,060
kWh
|
$9,519
-
kW-mo/yr
|
$431
-
MMBtu
|
$11,720
-
Tgal
|
$1,735
-
lb
|
$2,754 |
$6,403
-
Tgal
|
$364 | ||
TOTAL IMPLEMENTED | $11,381 | $1,089 |
$6,186
268,171
kWh
|
$4,200
-
kW-mo/yr
|
- |
$631
-
Tgal
|
- | - | - | $364 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Water Consumption Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs