Assessment Year | 1996 |
---|---|
Principal Product | polyethylene pipe |
NAICS |
n/a
|
SIC | 3084: Plastics Pipe |
Sales Range | $10 M to 50M |
# of Employees | 74 |
Plant Area |
150,000
ft2
|
Annual Production | 30,000,000
lb
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $308,721 | 13,273,154 |
kWh
|
$0.023 |
Electricity Demand | $195,985 | 25,500 |
kW-mo/yr
|
$7.69 |
Natural Gas | $20,126 | 4,780 |
MMBtu
|
$4.21 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $29,095 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $21,859 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,211 | $6,599 |
$1,550
66,530
kWh
|
$661
-
kW-mo/yr
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $465 | $516 |
$343
14,654
kWh
|
$122
-
kW-mo/yr
|
- | - | - | |
03 | 2.6231: Utilize controls to operate equipment only when needed | $945 | $260 |
$945
40,445
kWh
|
- | - | - | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $971 | $2,560 |
$743
31,946
kWh
|
$228
-
kW-mo/yr
|
- | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $697 | $222 |
$519
22,274
kWh
|
$178
-
kW-mo/yr
|
- | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $623 | $160 |
$459
19,637
kWh
|
$164
-
kW-mo/yr
|
- | - | - | |
07 | 2.3212: Optimize plant power factor | $11,884 | $22,134 | - | - | - | - | $11,884 | |
08 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $6,291 | - | - | - |
$6,291
-
lb
|
- | - | |
09 | 3.7121: Improve handling practices | $5,008 | $2,000 | - | - | - |
$5,008
-
lb
|
- | |
TOTAL RECOMMENDED | $29,095 | $34,451 |
$4,559
195,486
kWh
|
$1,353
-
kW-mo/yr
|
$6,291
-
lb
|
$5,008
-
lb
|
$11,884 | ||
TOTAL IMPLEMENTED | $21,859 | $34,191 |
$3,614
155,041
kWh
|
$1,353
-
kW-mo/yr
|
- |
$5,008
-
lb
|
$11,884 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs