ITAC Assessment: OK0636
ITAC logo
ITAC Assessment: OK0636
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Fabricated Metal
NAICS
n/a
SIC 3559: Special Industry Machinery, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 450
Plant Area 188,000
ft2
Annual Production 10,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $169,889 6,584,832
kWh
Electricity Fees $15,695 -
Natural Gas $66,048 17,109
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $216,512 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $192,175

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $5,565 $16,300 $5,565
215,654
kWh
- - -
02 2.2514: Cover open tanks $2,412 $528 - $2,412
-
MMBtu
- -
03 2.2437: Recover waste heat from equipment $6,525 $1,500 - $6,525
-
MMBtu
- -
04 2.7141: Lower light fixtures in high ceiling areas $175,200 $12,800 - - - $175,200
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $11,410 $1,400 $12,160
471,330
kWh
- - $(-750.0)
06 3.6123: Burn wood by-products for heat $15,400 $22,800 - $4,200
-
MMBtu
$16,000
-
lb
$(-4,800.0)
TOTAL RECOMMENDED $216,512 $55,328 $17,725
686,984
kWh
$13,137
-
MMBtu
$16,000
-
lb
$169,650
TOTAL IMPLEMENTED $192,175 $30,500 $17,725
686,984
kWh
- - $174,450
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs