| Assessment Year | 2002 |
|---|---|
| Principal Product | Fabricated Metal |
| NAICS |
n/a
|
| SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 450 |
| Plant Area |
188,000
ft2
|
| Annual Production | 10,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $169,889 | 6,584,832 |
kWh
|
$0.026 |
| Electricity Fees | $15,695 | - |
|
- |
| Natural Gas | $66,048 | 17,109 |
MMBtu
|
$3.86 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $216,512 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $192,175 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,565 | $16,300 |
$5,565
215,654
kWh
|
- | - | - | |
| 02 | 2.2514: Cover open tanks | $2,412 | $528 | - |
$2,412
-
MMBtu
|
- | - | |
| 03 | 2.2437: Recover waste heat from equipment | $6,525 | $1,500 | - |
$6,525
-
MMBtu
|
- | - | |
| 04 | 2.7141: Lower light fixtures in high ceiling areas | $175,200 | $12,800 | - | - | - | $175,200 | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,410 | $1,400 |
$12,160
471,330
kWh
|
- | - | $(-750.0) | |
| 06 | 3.6123: Burn wood by-products for heat | $15,400 | $22,800 | - |
$4,200
-
MMBtu
|
$16,000
-
lb
|
$(-4,800.0) | |
| TOTAL RECOMMENDED | $216,512 | $55,328 |
$17,725
686,984
kWh
|
$13,137
-
MMBtu
|
$16,000
-
lb
|
$169,650 | ||
| TOTAL IMPLEMENTED | $192,175 | $30,500 |
$17,725
686,984
kWh
|
- | - | $174,450 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs