ITAC Assessment: IA0128
ITAC logo
ITAC Assessment: IA0128
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Printing of specialty ads on calenders
NAICS
n/a
SIC 2752: Commercial Printing, Lithographic
Sales Range $10
M
to 50
M
# of Employees 350
Plant Area 210,000
ft2
Annual Production 42,200,000
pieces
Production Hrs. Annual 2,340
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $63,263 1,481,243
kWh
Natural Gas $14,081 4,664
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,904 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,578

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $6,615 $14,547 $6,615
154,748
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,142 $677 $1,142
26,671
kWh
-
03 2.4221: Install compressor air intakes in coolest locations $264 $220 $264
6,155
kWh
-
04 2.4231: Reduce the pressure of compressed air to the minimum required $230 $25 $230
5,275
kWh
-
05 2.7447: Install vinyl strip / high speed / air curtain doors $326 $448 $93
2,052
kWh
$233
-
MMBtu
06 2.7135: Install occupancy sensors $187 $604 $187
4,396
kWh
-
07 2.6218: Turn off equipment when not in use $140 $25 $140
3,224
kWh
-
TOTAL RECOMMENDED $8,904 $16,546 $8,671
202,521
kWh
$233
-
MMBtu
TOTAL IMPLEMENTED $8,578 $16,098 $8,578
200,469
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs