| Assessment Year | 2014 |
|---|---|
| Principal Product | injection molded products |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 93 |
| Plant Area |
90,200
ft2
|
| Annual Production | 1,000,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $238,637 | 5,738,797 |
kWh
|
$0.042 |
| Electricity Demand | $63,139 | 12,557 |
kW-mo/yr
|
$5.03 |
| Electricity Fees | $14,002 | - |
|
- |
| Fuel Oil #2 | $48,933 | 1,964 |
MMBtu
|
$24.91 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $13,830 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,722 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.8121: Apply for tax-free status for energy purchases | $3,785 | - | - | - | $3,785 | |
| 02 | 2.4322: Use or replace with energy efficient substitutes | $1,155 | - |
$702
16,875
kWh
|
$453
-
kW-mo/yr
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,427 | $100 |
$1,427
34,304
kWh
|
- | - | |
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $2,111 | $527 |
$1,713
41,184
kWh
|
$398
-
kW-mo/yr
|
- | |
| 05 | 2.7135: Install occupancy sensors | $320 | $100 |
$320
7,687
kWh
|
- | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $913 | $646 |
$913
21,955
kWh
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $712 | $582 |
$61
1,472
kWh
|
$10
-
kW-mo/yr
|
$641 | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,369 | $3,256 |
$1,111
26,708
kWh
|
$258
-
kW-mo/yr
|
- | |
| 09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,775 | $6,702 |
$1,775
42,670
kWh
|
- | - | |
| 10 | 2.4321: Upgrade obsolete equipment | $263 | $1,078 |
$226
5,331
kWh
|
$37
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $13,830 | $12,991 |
$8,248
198,186
kWh
|
$1,156
-
kW-mo/yr
|
$4,426 | ||
| TOTAL IMPLEMENTED | $2,722 | $1,860 |
$2,034
48,794
kWh
|
$47
-
kW-mo/yr
|
$641 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs