ITAC Assessment: SU0367
ITAC logo
ITAC Assessment: SU0367
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product injection molded products
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 93
Plant Area 90,200
ft2
Annual Production 1,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $238,637 5,738,797
kWh
Electricity Demand $63,139 12,557
kW-mo/yr
Electricity Fees $14,002 -
Fuel Oil #2 $48,933 1,964
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,830 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,722

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
01 2.8121: Apply for tax-free status for energy purchases $3,785 - - - $3,785
02 2.4322: Use or replace with energy efficient substitutes $1,155 - $702
16,875
kWh
$453
-
kW-mo/yr
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,427 $100 $1,427
34,304
kWh
- -
04 2.7111: Reduce illumination to minimum necessary levels $2,111 $527 $1,713
41,184
kWh
$398
-
kW-mo/yr
-
05 2.7135: Install occupancy sensors $320 $100 $320
7,687
kWh
- -
06 2.4221: Install compressor air intakes in coolest locations $913 $646 $913
21,955
kWh
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $712 $582 $61
1,472
kWh
$10
-
kW-mo/yr
$641
08 2.7142: Utilize higher efficiency lamps and/or ballasts $1,369 $3,256 $1,111
26,708
kWh
$258
-
kW-mo/yr
-
09 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,775 $6,702 $1,775
42,670
kWh
- -
10 2.4321: Upgrade obsolete equipment $263 $1,078 $226
5,331
kWh
$37
-
kW-mo/yr
-
TOTAL RECOMMENDED $13,830 $12,991 $8,248
198,186
kWh
$1,156
-
kW-mo/yr
$4,426
TOTAL IMPLEMENTED $2,722 $1,860 $2,034
48,794
kWh
$47
-
kW-mo/yr
$641
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs