Assessment Year | 1994 |
---|---|
Principal Product | plastic pipe |
NAICS |
n/a
|
SIC | 3084: Plastics Pipe |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
130,000
ft2
|
Annual Production | 50,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $344,148 | 7,972,450 |
kWh
|
$0.043 |
Natural Gas | $5,894 | 1,262 |
MMBtu
|
$4.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $20,198 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,189 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $431 | $390 |
$171
4,103
kWh
|
$260
-
MMBtu
|
|
02 | 2.3212: Optimize plant power factor | $6,631 | $22,020 |
$6,631
-
kWh
|
- | |
03 | 2.2511: Insulate bare equipment | $5,786 | $545 |
$5,786
133,939
kWh
|
- | |
04 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $5,074 | $800 |
$5,074
117,526
kWh
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,758 | $250 |
$1,758
40,739
kWh
|
- | |
06 | 2.7111: Reduce illumination to minimum necessary levels | $325 | $150 |
$325
7,620
kWh
|
- | |
07 | 2.7135: Install occupancy sensors | $193 | $516 |
$193
4,396
kWh
|
- | |
TOTAL RECOMMENDED | $20,198 | $24,671 |
$19,938
308,323
kWh
|
$260
-
MMBtu
|
||
TOTAL IMPLEMENTED | $2,189 | $640 |
$1,929
44,842
kWh
|
$260
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs