ITAC Assessment: IA0084
ITAC logo
ITAC Assessment: IA0084
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product plastic pipe
NAICS
n/a
SIC 3084: Plastics Pipe
Sales Range $10
M
to 50
M
# of Employees 70
Plant Area 130,000
ft2
Annual Production 50,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $344,148 7,972,450
kWh
Natural Gas $5,894 1,262
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,198 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,189

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7261: Install timers and/or thermostats $431 $390 $171
4,103
kWh
$260
-
MMBtu
02 2.3212: Optimize plant power factor $6,631 $22,020 $6,631
-
kWh
-
03 2.2511: Insulate bare equipment $5,786 $545 $5,786
133,939
kWh
-
04 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $5,074 $800 $5,074
117,526
kWh
-
05 2.4221: Install compressor air intakes in coolest locations $1,758 $250 $1,758
40,739
kWh
-
06 2.7111: Reduce illumination to minimum necessary levels $325 $150 $325
7,620
kWh
-
07 2.7135: Install occupancy sensors $193 $516 $193
4,396
kWh
-
TOTAL RECOMMENDED $20,198 $24,671 $19,938
308,323
kWh
$260
-
MMBtu
TOTAL IMPLEMENTED $2,189 $640 $1,929
44,842
kWh
$260
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs