| Assessment Year | 1993 |
|---|---|
| Principal Product | PROCESSED HAM |
| NAICS |
n/a
|
| SIC | 2013: Sausages and Other Prepared Meat Products |
| Sales Range | $100 M to 500M |
| # of Employees | 220 |
| Plant Area |
n/a
|
| Annual Production | 101,000,000
lb
|
| Production Hrs. Annual | 5,200
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $435,684 | 9,012,896 |
kWh
|
$0.048 |
| Natural Gas | $204,373 | 75,241 |
MMBtu
|
$2.72 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $157,831 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $21,570 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $90,934 | $267,950 |
$111,958
2,696,366
kWh
|
$(-23,224.0)
-
MMBtu
|
$2,200 | |
| 02 | 2.2621: Modify refrigeration system to operate at a lower pressure | $42,651 | $56,888 |
$42,651
882,181
kWh
|
- | - | |
| 03 | 2.4133: Use most efficient type of electric motors | $10,851 | $4,308 |
$10,851
224,502
kWh
|
- | - | |
| 04 | 2.2511: Insulate bare equipment | $1,822 | $7,616 | - |
$1,822
-
MMBtu
|
- | |
| 05 | 2.7261: Install timers and/or thermostats | $1,747 | $20 |
$1,250
25,791
kWh
|
$497
-
MMBtu
|
- | |
| 06 | 2.1213: Direct warmest air to combustion intake | $585 | $500 | - |
$585
-
MMBtu
|
- | |
| 07 | 2.4239: Eliminate or reduce compressed air usage | $3,637 | $1,000 |
$3,637
75,322
kWh
|
- | - | |
| 08 | 2.4221: Install compressor air intakes in coolest locations | $2,476 | $200 |
$2,476
51,290
kWh
|
- | - | |
| 09 | 2.7135: Install occupancy sensors | $1,037 | - |
$1,689
34,877
kWh
|
- | $(-652.0) | |
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,188 | $1,430 |
$1,188
24,619
kWh
|
- | - | |
| 11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $903 | $360 |
$903
18,757
kWh
|
- | - | |
| TOTAL RECOMMENDED | $157,831 | $340,272 |
$176,603
4,033,705
kWh
|
$(-20,320.0)
-
MMBtu
|
$1,548 | ||
| TOTAL IMPLEMENTED | $21,570 | $13,144 |
$19,903
411,782
kWh
|
$2,319
-
MMBtu
|
$(-652.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs