| Assessment Year | 1992 |
|---|---|
| Principal Product | FROZEN VEGETABLES |
| NAICS |
n/a
|
| SIC | 2037: Frozen Fruits, Fruit Juices, and Vegetables |
| Sales Range | $10 M to 50M |
| # of Employees | 300 |
| Plant Area |
n/a
|
| Annual Production | 50,000,000
lb
|
| Production Hrs. Annual | 4,296
hrs
|
| Location (State) | Minnesota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $861,190 | 12,551,876 |
kWh
|
$0.069 |
| Natural Gas | $20,852 | 5,887 |
MMBtu
|
$3.54 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $453,900 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2621: Modify refrigeration system to operate at a lower pressure | $136,664 | $13,000 | n/a |
$136,664
1,991,794
kWh
|
- | - |
| 02 | 2.4133: Use most efficient type of electric motors | $1,994 | $16 | n/a |
$1,994
29,015
kWh
|
- | - |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,957 | $1,480 | n/a |
$4,715
68,581
kWh
|
- | $(-1,758.0) |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,986 | $8,825 | n/a |
$3,986
58,030
kWh
|
- | - |
| 05 | 2.6232: Install set-back timers | $1,114 | $1,188 | n/a |
$1,114
16,120
kWh
|
- | - |
| 06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,709 | $8,000 | n/a |
$1,709
24,912
kWh
|
- | - |
| 07 | 2.3212: Optimize plant power factor | $94,150 | $84,875 | n/a |
$94,150
-
kWh
|
- | - |
| 08 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $211,326 | $1 | n/a |
$485,573
7,806,858
kWh
|
$(-157,145.0)
-
MMBtu
|
$(-117,102.0) |
| TOTAL RECOMMENDED | $453,900 | $117,385 |
$729,905
9,995,310
kWh
|
$(-157,145.0)
-
MMBtu
|
$(-118,860.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs