ITAC Assessment: CO0031
ITAC logo
ITAC Assessment: CO0031
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product PUMPS & COMPRESSORS
NAICS
n/a
SIC 3561: Pumps and Pumping Equipment
Sales Range n/a
# of Employees 340
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 6,864
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $306,690 5,700,762
kWh
Natural Gas $36,937 7,621
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $40,365 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,694

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $1,774 $300 - $1,774
-
MMBtu
02 2.4322: Use or replace with energy efficient substitutes $10,968 $58,000 $10,968
203,986
kWh
-
03 2.3191: Use demand controller or load shedder $11,624 $1,200 $11,624
-
kWh
-
04 2.4131: Size electric motors for peak operating efficiency $9,585 $15,000 $9,585
178,195
kWh
-
05 2.7243: Improve air circulation with destratification fans / other methods $1,602 $10,000 $(-1,182.0)
(-21,981)
kWh
$2,784
-
MMBtu
06 2.3512: De-energize excess transformer capacity $920 $250 $920
16,999
kWh
-
07 2.2223: Enhance sensitivity of temperature control and cutoff $3,892 $600 $3,892
72,392
kWh
-
TOTAL RECOMMENDED $40,365 $85,350 $35,807
449,591
kWh
$4,558
-
MMBtu
TOTAL IMPLEMENTED $2,694 $550 $920
16,999
kWh
$1,774
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs