ITAC Assessment: GT0126
ITAC logo
ITAC Assessment: GT0126
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product ALUMINUM CASTINGS
NAICS
n/a
SIC 3363: Aluminum Die-Castings
Sales Range $5
M
to 10
M
# of Employees 68
Plant Area
n/a
Annual Production 1,000,000
lb
Production Hrs. Annual 2,080
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $30,377 439,039
kWh
Natural Gas $107,598 27,384
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,522 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,537

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2443: Re-use or recycle hot or cold process exhaust air $9,264 $5,890 - $9,264
-
MMBtu
02 2.2514: Cover open tanks $6,304 $460 - $6,304
-
MMBtu
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,537 $140 $2,537
40,445
kWh
-
04 2.4221: Install compressor air intakes in coolest locations $417 $400 $417
6,741
kWh
-
TOTAL RECOMMENDED $18,522 $6,890 $2,954
47,186
kWh
$15,568
-
MMBtu
TOTAL IMPLEMENTED $2,537 $140 $2,537
40,445
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs