ITAC Assessment: HO0233
ITAC logo
ITAC Assessment: HO0233
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Newspaper Printing
NAICS
n/a
SIC 2711: Newspapers: Publishing, or Publishing and Printing
Sales Range $10
M
to 50
M
# of Employees 96
Plant Area 50,000
ft2
Annual Production 10,000
ton
Production Hrs. Annual 8,112
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $97,503 1,727,433
kWh
Electricity Demand $125,233 5,682
kW-mo/yr
Electricity Fees $9,057 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $703,539 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $151,040

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,704 $12,835 $3,390
60,082
kWh
$2,314
-
kW-mo/yr
- - -
02 2.7135: Install occupancy sensors $822 $800 $822
14,654
kWh
- - - -
03 2.7124: Make a practice of turning off lights when not needed $1,080 - $1,080
19,050
kWh
- - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $17,361 $400 $17,361
306,565
kWh
- - - -
05 2.4221: Install compressor air intakes in coolest locations $3,490 $2,000 $2,220
39,273
kWh
$1,270
-
kW-mo/yr
- - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $4,314 $90 $2,727
48,359
kWh
$1,587
-
kW-mo/yr
- - -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,000 $8,023 - - - - $4,000
08 2.4156: Establish a preventative maintenance program $53,379 $4,000 - - - - $53,379
09 4.611: Begin a practice of predictive / preventative maintenance $840 $25 - - - - $840
10 4.611: Begin a practice of predictive / preventative maintenance $2,520 $2,150 - - - - $2,520
11 4.611: Begin a practice of predictive / preventative maintenance $2,500 $5,250 - - - - $2,500
12 4.444: Install system to collect scrap $4,436 $1,000 - - - - $4,436
13 4.652: Replace existing equipment with more suitable substitutes $5,400 $750 - - - - $5,400
14 4.444: Install system to collect scrap $2,535 - - - - - $2,535
15 4.513: Re-arrange equipment layout to reduce labor costs $2,880 $480 - - - - $2,880
16 4.441: Install automatic packing equipment $425,880 $50,000 - - - - $425,880
17 4.441: Install automatic packing equipment $21,294 $7,000 - - - - $21,294
18 3.1111: Cover ink containers when not in use $12,884 - - - - $12,884
-
lb
-
19 3.7121: Improve handling practices $3,720 $500 - - $3,720
-
lb
- -
20 3.1191: Change procedures / equipment / operating conditions $53,000 $1,000 - - $53,000
-
lb
- -
21 3.5217: Reuse / recycle/ sell paper products $22,500 $1,000 - - $22,500
-
lb
- -
22 3.1192: Reduce scrap production $53,000 $1,000 - - $53,000
-
lb
- -
TOTAL RECOMMENDED $703,539 $98,303 $27,600
487,983
kWh
$5,171
-
kW-mo/yr
$132,220
-
lb
$12,884
-
lb
$525,664
TOTAL IMPLEMENTED $151,040 $18,925 $20,661
364,888
kWh
$1,270
-
kW-mo/yr
$79,220
-
lb
$12,884
-
lb
$37,005
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs