Assessment Year | 2000 |
---|---|
Principal Product | Frozen Breakfast Foods |
NAICS |
n/a
|
SIC | 2053: Frozen Bakery Products, Except Bread |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
190,000
ft2
|
Annual Production | 6,000,000
pieces
|
Production Hrs. Annual | 6,600
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $621,889 | 12,602,286 |
kWh
|
$0.049 |
Electricity Demand | $160,571 | 25,898 |
kW-mo/yr
|
$6.20 |
Electricity Fees | $(-49,887.0) | - |
|
- |
Natural Gas | $155,797 | 91,995 |
MMBtu
|
$1.69 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $335,037 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $212,603 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Primary Raw Material Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7124: Make a practice of turning off lights when not needed | $6,008 | - |
$6,008
121,630
kWh
|
- | - | - | - | - | |
02 | 2.7135: Install occupancy sensors | $2,854 | $5,000 |
$2,854
57,737
kWh
|
- | - | - | - | - | |
03 | 2.2511: Insulate bare equipment | $5,519 | $9,992 | - | - |
$5,519
-
MMBtu
|
- | - | - | |
04 | 2.2511: Insulate bare equipment | $3,996 | $5,204 | - | - |
$3,996
-
MMBtu
|
- | - | - | |
05 | 2.1211: Move boiler to more efficient location | $1,070 | $200 |
$538
10,844
kWh
|
$452
-
kW-mo/yr
|
- | - | - | $80 | |
06 | 2.4221: Install compressor air intakes in coolest locations | $1,350 | $3,000 |
$1,099
22,274
kWh
|
$251
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $9,373 | $2,790 |
$9,373
189,918
kWh
|
- | - | - | - | - | |
08 | 2.6218: Turn off equipment when not in use | $398 | - |
$398
8,206
kWh
|
- | - | - | - | - | |
09 | 2.4156: Establish a preventative maintenance program | $85,091 | $4,000 | - | - | - | - | - | $85,091 | |
10 | 3.7221: Improve process control to prevent spills of material | $73,575 | - | - | - | - | - | $73,125 | $450 | |
11 | 4.611: Begin a practice of predictive / preventative maintenance | $15,600 | $300 | - | - | - | - | - | $15,600 | |
12 | 4.611: Begin a practice of predictive / preventative maintenance | $15,600 | $3,000 | - | - | - | - | - | $15,600 | |
13 | 4.444: Install system to collect scrap | $12,375 | $1,075 | - | - | - | - | - | $12,375 | |
14 | 4.124: Install continuous lubrication equipment | $5,850 | $20,000 | - | - | - | - | - | $5,850 | |
15 | 4.424: Improve space comfort conditioning | $2,880 | $200 | - | - | - | - | - | $2,880 | |
16 | 3.4154: Eliminate leaks in water lines and valves | $1,980 | $20,017 | - | - | - |
$1,980
-
Tgal
|
- | - | |
17 | 3.3128: Utilize other methods to remove contaminants | $79,092 | $7,100 | - | - | - | - | - | $79,092 | |
18 | 3.5311: Recover and reuse waste material | $7,809 | $2,360 | - | - | - | - | - | $7,809 | |
19 | 3.4113: Treat and reuse rinse waters | $4,617 | $10,100 | - | - | - |
$4,617
-
Tgal
|
- | - | |
TOTAL RECOMMENDED | $335,037 | $94,338 |
$20,270
410,609
kWh
|
$703
-
kW-mo/yr
|
$9,515
-
MMBtu
|
$6,597
-
Tgal
|
$73,125 | $224,827 | ||
TOTAL IMPLEMENTED | $212,603 | $31,317 |
$18,633
377,491
kWh
|
- |
$5,519
-
MMBtu
|
- | $73,125 | $115,326 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Primary Raw Material Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs