Assessment Year | 2000 |
---|---|
Principal Product | Wood Dash Kits |
NAICS |
n/a
|
SIC | 3083: Laminated Plastics Plate, Sheet, and Profile Shapes |
Sales Range | $100 M to 500M |
# of Employees | 140 |
Plant Area |
85,000
ft2
|
Annual Production | 140,400
pieces
|
Production Hrs. Annual | 4,056
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $32,367 | 525,791 |
kWh
|
$0.062 |
Electricity Demand | $34,136 | 1,742 |
kW-mo/yr
|
$19.60 |
Electricity Fees | $4,612 | - |
|
- |
Natural Gas | $17,390 | 4,369 |
MMBtu
|
$3.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $169,290 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $148,999 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,864 | $8,232 |
$2,513
40,739
kWh
|
$2,351
-
kW-mo/yr
|
- | - | |
02 | 2.6218: Turn off equipment when not in use | $1,158 | - |
$653
10,551
kWh
|
$505
-
kW-mo/yr
|
- | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $455 | $1,000 |
$286
4,689
kWh
|
$169
-
kW-mo/yr
|
- | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $538 | $15 |
$278
4,396
kWh
|
$260
-
kW-mo/yr
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,054 | $200 |
$1,054
16,999
kWh
|
- | - | - | |
06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,810 | $778 | - | - |
$1,810
-
MMBtu
|
- | |
07 | 4.321: Optimize production lot sizes and inventories | $9,360 | $5,000 | - | - | - | $9,360 | |
08 | 4.515: Install shelves / racks to utilize unused space | $9,360 | $25,000 | - | - | - | $9,360 | |
09 | 4.424: Improve space comfort conditioning | $2,880 | $2,340 | - | - | - | $2,880 | |
10 | 4.213: Purchase material from supplier in customized packaging | $10,395 | $3,000 | - | - | - | $10,395 | |
11 | 4.111: Add equipment/ operators to reduce production bottleneck | $68,250 | $300,000 | - | - | - | $68,250 | |
12 | 4.652: Replace existing equipment with more suitable substitutes | $1,440 | $1,500 | - | - | - | $1,440 | |
13 | 4.423: Move product using mechanical means | $6,240 | $2,500 | - | - | - | $6,240 | |
14 | 4.513: Re-arrange equipment layout to reduce labor costs | $39,000 | $6,000 | - | - | - | $39,000 | |
15 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $3,456 | $6,500 | - | - | - | $3,456 | |
16 | 4.652: Replace existing equipment with more suitable substitutes | $780 | $750 | - | - | - | $780 | |
17 | 3.7214: Reduce or eliminate waste | $8,250 | - | - | - | - | $8,250 | |
TOTAL RECOMMENDED | $169,290 | $362,815 |
$4,784
77,374
kWh
|
$3,285
-
kW-mo/yr
|
$1,810
-
MMBtu
|
$159,411 | ||
TOTAL IMPLEMENTED | $148,999 | $327,065 |
$4,498
72,685
kWh
|
$3,116
-
kW-mo/yr
|
$1,810
-
MMBtu
|
$139,575 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs