Assessment Year | 1999 |
---|---|
Principal Product | Pressure-sensitive tape |
NAICS |
n/a
|
SIC | 2672: Coated and Laminated Paper, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 130 |
Plant Area |
226,000
ft2
|
Annual Production | 1,350,000
thousand feet
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $300,190 | 3,679,953 |
kWh
|
$0.082 |
Electricity Demand | $86,199 | 9,576 |
kW-mo/yr
|
$9.00 |
Electricity Fees | $(-36,490.0) | - |
|
- |
Natural Gas | $156,848 | 39,152 |
MMBtu
|
$4.01 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $69,820 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $35,646 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,922 | $12,583 |
$5,332
65,358
kWh
|
$2,590
-
kW-mo/yr
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,560 | $11,408 |
$6,237
76,495
kWh
|
$1,323
-
kW-mo/yr
|
- | - | - | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $1,069 | - |
$1,069
13,189
kWh
|
- | - | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $8,757 | $5,030 |
$8,757
107,268
kWh
|
- | - | - | - | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $2,237 | $833 | - | - |
$2,237
-
MMBtu
|
- | - | |
06 | 2.8114: Change rate schedules or other changes in utility service | $24,015 | $27,500 | - | - | - | - | $24,015 | |
07 | 2.6231: Utilize controls to operate equipment only when needed | $18,260 | $24,000 | - | - | - |
$18,260
-
Tgal
|
- | |
TOTAL RECOMMENDED | $69,820 | $81,354 |
$21,395
262,310
kWh
|
$3,913
-
kW-mo/yr
|
$2,237
-
MMBtu
|
$18,260
-
Tgal
|
$24,015 | ||
TOTAL IMPLEMENTED | $35,646 | $40,438 |
$16,063
196,952
kWh
|
$1,323
-
kW-mo/yr
|
- |
$18,260
-
Tgal
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs