| Assessment Year | 2013 |
|---|---|
| Principal Product | Ceramic Body Armor Tiles |
| NAICS | 327999: All Other Miscellaneous Nonmetallic Mineral Product Manufacturing |
| SIC | 3299: Nonmetallic Mineral Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 220 |
| Plant Area |
115,000
ft2
|
| Annual Production | 450,000
pieces
|
| Production Hrs. Annual | 7,728
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $993,013 | 28,116,425 |
kWh
|
$0.035 |
| Electricity Demand | $473,275 | 68,317 |
kW-mo/yr
|
$6.93 |
| Electricity Fees | $221,153 | - |
|
- |
| Natural Gas | $358,789 | 75,751 |
MMBtu
|
$4.74 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $51,024 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $48,264 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $16,665 | $200 |
$16,665
472,104
kWh
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,284 | $88,771 |
$14,492
411,720
kWh
|
$2,792
-
kW-mo/yr
|
|
| 03 | 2.6218: Turn off equipment when not in use | $7,500 | $5,600 |
$7,500
212,000
kWh
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,278 | $27,331 |
$3,370
95,450
kWh
|
$908
-
kW-mo/yr
|
|
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,537 | $1,340 |
$2,537
71,870
kWh
|
- | |
| 06 | 2.7135: Install occupancy sensors | $2,760 | $3,342 |
$2,760
78,210
kWh
|
- | |
| TOTAL RECOMMENDED | $51,024 | $126,584 |
$47,324
1,341,354
kWh
|
$3,700
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $48,264 | $123,242 |
$44,564
1,263,144
kWh
|
$3,700
-
kW-mo/yr
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs