ITAC Assessment: UK1311
ITAC logo
ITAC Assessment: UK1311
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Ceramic Body Armor Tiles
NAICS 327999: All Other Miscellaneous Nonmetallic Mineral Product Manufacturing
SIC 3299: Nonmetallic Mineral Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 220
Plant Area 115,000
ft2
Annual Production 450,000
pieces
Production Hrs. Annual 7,728
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $993,013 28,116,425
kWh
Electricity Demand $473,275 68,317
kW-mo/yr
Electricity Fees $221,153 -
Natural Gas $358,789 75,751
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $51,024 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $48,264

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.6218: Turn off equipment when not in use $16,665 $200 $16,665
472,104
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $17,284 $88,771 $14,492
411,720
kWh
$2,792
-
kW-mo/yr
03 2.6218: Turn off equipment when not in use $7,500 $5,600 $7,500
212,000
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $4,278 $27,331 $3,370
95,450
kWh
$908
-
kW-mo/yr
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,537 $1,340 $2,537
71,870
kWh
-
06 2.7135: Install occupancy sensors $2,760 $3,342 $2,760
78,210
kWh
-
TOTAL RECOMMENDED $51,024 $126,584 $47,324
1,341,354
kWh
$3,700
-
kW-mo/yr
TOTAL IMPLEMENTED $48,264 $123,242 $44,564
1,263,144
kWh
$3,700
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs