Assessment Year | 2013 |
---|---|
Principal Product | Ceramic Body Armor Tiles |
NAICS | 327999: All Other Miscellaneous Nonmetallic Mineral Product Manufacturing |
SIC | 3299: Nonmetallic Mineral Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 220 |
Plant Area |
115,000
ft2
|
Annual Production | 450,000
pieces
|
Production Hrs. Annual | 7,728
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $993,013 | 28,116,425 |
kWh
|
$0.035 |
Electricity Demand | $473,275 | 68,317 |
kW-mo/yr
|
$6.93 |
Electricity Fees | $221,153 | - |
|
- |
Natural Gas | $358,789 | 75,751 |
MMBtu
|
$4.74 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $51,024 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $48,264 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $16,665 | $200 |
$16,665
472,104
kWh
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,284 | $88,771 |
$14,492
411,720
kWh
|
$2,792
-
kW-mo/yr
|
|
03 | 2.6218: Turn off equipment when not in use | $7,500 | $5,600 |
$7,500
212,000
kWh
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,278 | $27,331 |
$3,370
95,450
kWh
|
$908
-
kW-mo/yr
|
|
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,537 | $1,340 |
$2,537
71,870
kWh
|
- | |
06 | 2.7135: Install occupancy sensors | $2,760 | $3,342 |
$2,760
78,210
kWh
|
- | |
TOTAL RECOMMENDED | $51,024 | $126,584 |
$47,324
1,341,354
kWh
|
$3,700
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $48,264 | $123,242 |
$44,564
1,263,144
kWh
|
$3,700
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs