Assessment Year | 1999 |
---|---|
Principal Product | Custom Stamped Metal Parts |
NAICS |
n/a
|
SIC | 3469: Metal Stampings, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 40 |
Plant Area |
35,000
ft2
|
Annual Production | 250,000
lb
|
Production Hrs. Annual | 4,500
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $86,070 | 997,069 |
kWh
|
$0.086 |
Electricity Demand | $23,855 | 2,666 |
kW-mo/yr
|
$8.95 |
Electricity Fees | $(-8,882.0) | - |
|
- |
Natural Gas | $435 | 15 |
MMBtu
|
$29.00 |
Fuel Oil #2 | $39,139 | 8,559 |
MMBtu
|
$4.57 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $38,085 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,296 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Water Disposal Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,583 | $16,842 |
$8,364
97,011
kWh
|
$2,219
-
kW-mo/yr
|
- | - | - | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $901 | - |
$901
10,551
kWh
|
- | - | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $393 | $492 |
$393
22,274
kWh
|
- | - | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $1,928 | $2,000 |
$1,520
17,585
kWh
|
$408
-
kW-mo/yr
|
- | - | - | |
05 | 2.2136: Install / repair insulation on steam lines | $1,517 | $1,424 | - | - |
$1,517
-
MMBtu
|
- | - | |
06 | 2.2123: Insulate feedwater tank | $526 | $438 | - | - |
$526
-
MMBtu
|
- | - | |
07 | 2.6231: Utilize controls to operate equipment only when needed | $3,911 | $2,450 | - | - |
$3,911
-
MMBtu
|
- | - | |
08 | 2.2414: Use waste heat from hot flue gases to preheat | $1,470 | $483 | - | - |
$1,470
-
MMBtu
|
- | - | |
09 | 4.641: Eliminate shutdowns of controls due to overheating | $5,342 | $1,760 | - | - | - | - | $5,342 | |
10 | 4.653: Maintain/enlarge a stock of spare parts | $1,125 | $318 | - | - | - | - | $1,125 | |
11 | 4.611: Begin a practice of predictive / preventative maintenance | $600 | $250 | - | - | - | - | $600 | |
12 | 4.611: Begin a practice of predictive / preventative maintenance | $6,410 | $1,424 | - | - | - | - | $6,410 | |
13 | 4.611: Begin a practice of predictive / preventative maintenance | $2,250 | $120 | - | - | - | - | $2,250 | |
14 | 3.4151: Minimize water usage | $1,129 | $600 | - | - | - |
$1,129
-
Tgal
|
- | |
TOTAL RECOMMENDED | $38,085 | $28,601 |
$11,178
147,421
kWh
|
$2,627
-
kW-mo/yr
|
$7,424
-
MMBtu
|
$1,129
-
Tgal
|
$15,727 | ||
TOTAL IMPLEMENTED | $19,296 | $20,168 |
$9,265
107,562
kWh
|
$2,219
-
kW-mo/yr
|
$4,437
-
MMBtu
|
- | $3,375 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Water Disposal Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs