| Assessment Year | 2010 |
|---|---|
| Principal Product | Self-Locking fastners |
| NAICS | 332722: Bolt, Nut, Screw, Rivet, and Washer Manufacturing |
| SIC | 3452: Bolts, Nuts, Screws, Rivets, and Washers |
| Sales Range | $10 M to 50M |
| # of Employees | 75 |
| Plant Area |
120,000
ft2
|
| Annual Production | 50,000,000
pieces
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $217,706 | 2,354,000 |
kWh
|
$0.092 |
| Electricity Fees | $31,864 | - |
|
- |
| Natural Gas | $89,559 | 9,455 |
MMBtu
|
$9.47 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $23,330 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,871 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,558 | $4,290 |
$7,468
80,753
kWh
|
$1,090 | - | - | - | |
| 02 | 4.611: Begin a practice of predictive / preventative maintenance | $6,028 | $720 |
$3,951
42,718
kWh
|
$577 | - | - | $1,500 | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,236 | $13,160 |
$2,824
30,534
kWh
|
$412 | - | - | - | |
| 04 | 2.7135: Install occupancy sensors | $2,183 | $720 |
$1,905
20,601
kWh
|
$278 | - | - | - | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $1,802 | $450 |
$1,572
17,004
kWh
|
$230 | - | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $657 | $350 |
$308
3,329
kWh
|
$45 | - | $304 | - | |
| 07 | 2.2611: Moderate cooling tower outlet temperature | $553 | $467 |
$482
5,242
kWh
|
$71 | - | - | - | |
| 08 | 2.2511: Insulate bare equipment | $313 | $123 | - | - |
$313
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $23,330 | $20,280 |
$18,510
200,181
kWh
|
$2,703 |
$313
-
MMBtu
|
$304 | $1,500 | ||
| TOTAL IMPLEMENTED | $8,871 | $4,413 |
$7,468
80,753
kWh
|
$1,090 |
$313
-
MMBtu
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs