Assessment Year | 1997 |
---|---|
Principal Product | Carpet Swatch catalogs |
NAICS |
n/a
|
SIC | 2720: |
Sales Range | $10 M to 50M |
# of Employees | 225 |
Plant Area |
150,000
ft2
|
Annual Production | 500,000
lb
|
Production Hrs. Annual | 2,956
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $122,841 | 2,194,314 |
kWh
|
$0.056 |
Electricity Demand | $153,937 | 7,296 |
kW-mo/yr
|
$21.10 |
Electricity Fees | $40,393 | - |
|
- |
Natural Gas | $41,623 | 7,385 |
MMBtu
|
$5.64 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $35,983 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,800 | $33,870 |
$4,759
84,994
kWh
|
$7,041
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $168 | $358 |
$168
2,931
kWh
|
- | - | - | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $367 | $400 |
$159
2,931
kWh
|
$208
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $620 | $444 | - | - |
$620
-
MMBtu
|
- | - | - | |
05 | 4.441: Install automatic packing equipment | $8,160 | $35,000 | - | - | - | - | $8,160 | - | |
06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $968 | $750 | - | - |
$968
-
MMBtu
|
- | - | - | |
07 | 3.1191: Change procedures / equipment / operating conditions | $13,500 | - | - | - | - |
$15,000
-
lb
|
$(-1,500.0) | - | |
08 | 3.1191: Change procedures / equipment / operating conditions | $400 | $500 | - | - | - | - | - | $400 | |
TOTAL RECOMMENDED | $35,983 | $71,322 |
$5,086
90,856
kWh
|
$7,249
-
kW-mo/yr
|
$1,588
-
MMBtu
|
$15,000
-
lb
|
$6,660 | $400 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs