ITAC Assessment: HO0149
ITAC logo
ITAC Assessment: HO0149
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Carpet Swatch catalogs
NAICS
n/a
SIC 2720:
Sales Range $10
M
to 50
M
# of Employees 225
Plant Area 150,000
ft2
Annual Production 500,000
lb
Production Hrs. Annual 2,956
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $122,841 2,194,314
kWh
Electricity Demand $153,937 7,296
kW-mo/yr
Electricity Fees $40,393 -
Natural Gas $41,623 7,385
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $35,983 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $11,800 $33,870 $4,759
84,994
kWh
$7,041
-
kW-mo/yr
- - - -
02 2.4133: Use most efficient type of electric motors $168 $358 $168
2,931
kWh
- - - - -
03 2.4221: Install compressor air intakes in coolest locations $367 $400 $159
2,931
kWh
$208
-
kW-mo/yr
- - - -
04 2.2414: Use waste heat from hot flue gases to preheat $620 $444 - - $620
-
MMBtu
- - -
05 4.441: Install automatic packing equipment $8,160 $35,000 - - - - $8,160 -
06 2.7447: Install vinyl strip / high speed / air curtain doors $968 $750 - - $968
-
MMBtu
- - -
07 3.1191: Change procedures / equipment / operating conditions $13,500 - - - - $15,000
-
lb
$(-1,500.0) -
08 3.1191: Change procedures / equipment / operating conditions $400 $500 - - - - - $400
TOTAL RECOMMENDED $35,983 $71,322 $5,086
90,856
kWh
$7,249
-
kW-mo/yr
$1,588
-
MMBtu
$15,000
-
lb
$6,660 $400
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs