ITAC Assessment: HO0142
ITAC logo
ITAC Assessment: HO0142
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Plastic injection molding
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 100
Plant Area 28,000
ft2
Annual Production 1,000,000
lb
Production Hrs. Annual 5,760
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $200,977 1,894,490
kWh
Electricity Demand $42,760 3,818
kW-mo/yr
Natural Gas $6,090 580
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $51,589 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,261

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $6,261 $10,505 $5,051
44,256
kWh
$1,210
-
kW-mo/yr
- - -
02 2.4133: Use most efficient type of electric motors $750 $365 $750
6,448
kWh
- - - -
03 2.4221: Install compressor air intakes in coolest locations $1,003 $800 $833
7,327
kWh
$170
-
kW-mo/yr
- - -
04 2.7447: Install vinyl strip / high speed / air curtain doors $4,770 $750 - - $4,770
-
MMBtu
- -
05 2.6212: Turn off equipment during breaks, reduce operating time $23,805 - $23,805
206,038
kWh
- - - -
06 3.6193: Install equipment (eg compactor) to reduce disposal costs $12,000 $6,500 - - - - $12,000
-
lb
07 3.4111: Use closed cycle process to minimize waste water production $3,000 $6,750 - - - $3,000
-
Tgal
-
TOTAL RECOMMENDED $51,589 $25,670 $30,439
264,069
kWh
$1,380
-
kW-mo/yr
$4,770
-
MMBtu
$3,000
-
Tgal
$12,000
-
lb
TOTAL IMPLEMENTED $6,261 $10,505 $5,051
44,256
kWh
$1,210
-
kW-mo/yr
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs