| Assessment Year | 2002 |
|---|---|
| Principal Product | Street Sweepers |
| NAICS |
n/a
|
| SIC | 3537: Industrial Trucks, Tractors, Trailers, and Stackers |
| Sales Range | $100 M to 500M |
| # of Employees | 375 |
| Plant Area |
300,000
ft2
|
| Annual Production | 950
pieces
|
| Production Hrs. Annual | 5,610
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $200,112 | 5,268,366 |
kWh
|
$0.038 |
| Electricity Demand | $141,368 | 12,054 |
kW-mo/yr
|
$11.73 |
| Electricity Fees | $26,251 | - |
|
- |
| Natural Gas | $341,948 | 44,082 |
MMBtu
|
$7.76 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $114,060 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $39,996 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $24,405 | $97,350 |
$16,640
396,178
kWh
|
$9,940
-
kW-mo/yr
|
- | $(-1,527.0) | - | $(-648.0) | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,622 | $5,604 |
$918
21,861
kWh
|
$549
-
kW-mo/yr
|
- | $10 | - | $145 | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,219 | $1,700 |
$1,389
33,043
kWh
|
$1,830
-
kW-mo/yr
|
- | - | - | - | - | |
| 04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $11,179 | $15,000 | - | - |
$11,179
-
MMBtu
|
- | - | - | - | |
| 05 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $13,369 | $27,400 | - | - |
$13,369
-
MMBtu
|
- | - | - | - | |
| 06 | 4.322: Eliminate old stock and modify inventory control | $43,200 | $8,500 | - | - | - | - | $43,200 | - | - | |
| 07 | 3.1163: Use plastic pallets instead of wood | $10,750 | $22,000 | - | - | - | - | - | $10,750 | - | |
| 08 | 3.1181: Eliminate a by-product | $6,316 | $72,000 | - | - | - | - | - | - | $6,316 | |
| TOTAL RECOMMENDED | $114,060 | $249,554 |
$18,947
451,082
kWh
|
$12,319
-
kW-mo/yr
|
$24,548
-
MMBtu
|
$(-1,517.0) | $43,200 | $10,247 | $6,316 | ||
| TOTAL IMPLEMENTED | $39,996 | $126,654 |
$18,947
451,082
kWh
|
$12,319
-
kW-mo/yr
|
- | $(-1,517.0) | - | $10,247 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | By-product Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs