Assessment Year | 2002 |
---|---|
Principal Product | Street Sweepers |
NAICS |
n/a
|
SIC | 3537: Industrial Trucks, Tractors, Trailers, and Stackers |
Sales Range | $100 M to 500M |
# of Employees | 375 |
Plant Area |
300,000
ft2
|
Annual Production | 950
pieces
|
Production Hrs. Annual | 5,610
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $200,112 | 5,268,366 |
kWh
|
$0.038 |
Electricity Demand | $141,368 | 12,054 |
kW-mo/yr
|
$11.73 |
Electricity Fees | $26,251 | - |
|
- |
Natural Gas | $341,948 | 44,082 |
MMBtu
|
$7.76 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $114,060 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $39,996 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $24,405 | $97,350 |
$16,640
396,178
kWh
|
$9,940
-
kW-mo/yr
|
- | $(-1,527.0) | - | $(-648.0) | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,622 | $5,604 |
$918
21,861
kWh
|
$549
-
kW-mo/yr
|
- | $10 | - | $145 | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,219 | $1,700 |
$1,389
33,043
kWh
|
$1,830
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $11,179 | $15,000 | - | - |
$11,179
-
MMBtu
|
- | - | - | - | |
05 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $13,369 | $27,400 | - | - |
$13,369
-
MMBtu
|
- | - | - | - | |
06 | 4.322: Eliminate old stock and modify inventory control | $43,200 | $8,500 | - | - | - | - | $43,200 | - | - | |
07 | 3.1163: Use plastic pallets instead of wood | $10,750 | $22,000 | - | - | - | - | - | $10,750 | - | |
08 | 3.1181: Eliminate a by-product | $6,316 | $72,000 | - | - | - | - | - | - | $6,316 | |
TOTAL RECOMMENDED | $114,060 | $249,554 |
$18,947
451,082
kWh
|
$12,319
-
kW-mo/yr
|
$24,548
-
MMBtu
|
$(-1,517.0) | $43,200 | $10,247 | $6,316 | ||
TOTAL IMPLEMENTED | $39,996 | $126,654 |
$18,947
451,082
kWh
|
$12,319
-
kW-mo/yr
|
- | $(-1,517.0) | - | $10,247 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs