Assessment Year | 2011 |
---|---|
Principal Product | Multi-wall bags |
NAICS | 322220: Paper Bag and Coated and Treated Paper Manufacturing |
SIC | 2674: Uncoated Paper and Multiwall Bags |
Sales Range | $10 M to 50M |
# of Employees | 125 |
Plant Area |
300,000
ft2
|
Annual Production | 24,000
ton
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $298,190 | 5,324,822 |
kWh
|
$0.056 |
Electricity Demand | $169,213 | 10,716 |
kW-mo/yr
|
$15.79 |
Electricity Fees | $29,400 | - |
|
- |
Natural Gas | $91,242 | 9,041 |
MMBtu
|
$10.09 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $115,217 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $85,057 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $30,160 | $2,400 | - | - | - | $30,160 | |
02 | 3.4155: Meter waste water | $5,529 | $2,500 | - | - |
$5,529
-
Tgal
|
- | |
03 | 2.4151: Develop a repair/replace policy | $3,617 | $9,994 |
$1,826
31,110
kWh
|
$1,791
-
kW-mo/yr
|
- | - | |
04 | 2.4224: Upgrade controls on compressors | $51,129 | $25,000 |
$34,072
580,440
kWh
|
$17,057
-
kW-mo/yr
|
- | - | |
05 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $24,782 | $14,000 |
$13,888
236,590
kWh
|
$10,894
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $115,217 | $53,894 |
$49,786
848,140
kWh
|
$29,742
-
kW-mo/yr
|
$5,529
-
Tgal
|
$30,160 | ||
TOTAL IMPLEMENTED | $85,057 | $51,494 |
$49,786
848,140
kWh
|
$29,742
-
kW-mo/yr
|
$5,529
-
Tgal
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs