| Assessment Year | 2001 |
|---|---|
| Principal Product | Bakery Flour |
| NAICS |
n/a
|
| SIC | 2041: Flour and Other Grain Mill Products |
| Sales Range | $50 M to 100M |
| # of Employees | 30 |
| Plant Area |
30,000
ft2
|
| Annual Production | 180,000
ton
|
| Production Hrs. Annual | 7,448
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $587,068 | 11,329,455 |
kWh
|
$0.052 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $48,299 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,416 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,166 | - |
$2,166
34,497
kWh
|
- | |
| 02 | 2.6218: Turn off equipment when not in use | $641 | - |
$641
9,192
kWh
|
- | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $25,797 | $7,615 |
$25,797
369,487
kWh
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,718 | $776 |
$1,718
24,636
kWh
|
- | |
| 05 | 2.7135: Install occupancy sensors | $1,112 | $1,080 |
$1,112
15,946
kWh
|
- | |
| 06 | 2.4133: Use most efficient type of electric motors | $2,331 | $3,565 |
$2,331
33,442
kWh
|
- | |
| 07 | 2.7132: Install timers on light switches in little used areas | $1,971 | $4,170 |
$1,971
28,260
kWh
|
- | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $804 | $1,359 |
$804
11,532
kWh
|
- | |
| 09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,295 | $9,000 |
$3,295
47,235
kWh
|
- | |
| 10 | 3.5217: Reuse / recycle/ sell paper products | $1,230 | $90 | - |
$1,230
-
lb
|
|
| 11 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $7,234 | $15,374 | - |
$7,234
-
lb
|
|
| TOTAL RECOMMENDED | $48,299 | $43,029 |
$39,835
574,227
kWh
|
$8,464
-
lb
|
||
| TOTAL IMPLEMENTED | $9,416 | $8,601 |
$8,186
120,835
kWh
|
$1,230
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs