ITAC Assessment: UD0783
ITAC logo
ITAC Assessment: UD0783
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product automotive shift towers and control cables
NAICS 336320: Motor Vehicle Electrical and Electronic Equipment Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $50
M
to 100
M
# of Employees 365
Plant Area 145,000
ft2
Annual Production 3,000,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $504,750 10,579,200
kWh
Natural Gas $34,711 3,015
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $127,339 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.6218: Turn off equipment when not in use $26,465 - $26,465
1,017,900
kWh
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $25,926 $27,004 $10,128
456,000
kWh
$11,856
-
kW-mo/yr
- - $3,942
03 2.2511: Insulate bare equipment $23,572 $65,625 $11,606
446,400
kWh
$11,966
-
kW-mo/yr
- - -
04 2.2437: Recover waste heat from equipment $15,545 $10,000 - - $15,545
-
MMBtu
- -
05 2.7135: Install occupancy sensors $7,231 $7,200 $3,799
42,120
kWh
$2,304
-
kW-mo/yr
- - $1,128
06 2.7145: Install skylights $6,996 $40,770 $2,287
87,980
kWh
$4,709
-
kW-mo/yr
- - -
07 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $5,745 - $1,835
70,560
kWh
$3,910
-
kW-mo/yr
- - -
08 2.2437: Recover waste heat from equipment $4,324 - $1,599
61,200
kWh
$2,725
-
kW-mo/yr
- - -
09 2.7224: Reduce space conditioning during non-working hours $3,818 $5,000 - - $3,818
-
MMBtu
- -
10 2.4231: Reduce the pressure of compressed air to the minimum required $1,826 - $936
36,000
kWh
$890
-
kW-mo/yr
- - -
11 2.4221: Install compressor air intakes in coolest locations $1,659 $600 $842
32,400
kWh
$817
-
kW-mo/yr
- - -
12 2.4131: Size electric motors for peak operating efficiency $1,581 $500 $983
37,800
kWh
$598
-
kW-mo/yr
- - -
13 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $970 $1,000 $1,560
60,000
kWh
$1,330
-
kW-mo/yr
- $(-960.0) $(-960.0)
14 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $844 $500 $312
12,000
kWh
$532
-
kW-mo/yr
- - -
15 2.4239: Eliminate or reduce compressed air usage $837 $400 $452
17,400
kWh
$385
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $127,339 $158,599 $62,804
2,377,760
kWh
$42,022
-
kW-mo/yr
$19,363
-
MMBtu
$(-960.0) $4,110
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs