| Assessment Year | 2010 |
|---|---|
| Principal Product | Prepared Frozen Foods |
| NAICS | 311411: Frozen Fruit, Juice, and Vegetable Manufacturing |
| SIC | 2038: Frozen Specialties, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 290 |
| Plant Area |
20,800
ft2
|
| Annual Production | 12,000,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $293,202 | 6,448,615 |
kWh
|
$0.045 |
| Electricity Demand | $189,307 | 13,920 |
kW-mo/yr
|
$13.60 |
| Natural Gas | $115,317 | 18,157 |
MMBtu
|
$6.35 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $127,739 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $83,873 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $960 | $1,300 |
$960
20,135
kWh
|
- | - | |
| 02 | 2.4314: Use synthetic lubricant | $9,230 | - |
$9,230
193,920
kWh
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,954 | $19,633 |
$2,628
49,410
kWh
|
$2,326
-
kW-mo/yr
|
- | |
| 04 | 2.4322: Use or replace with energy efficient substitutes | $487 | $150,000 |
$487
10,230
kWh
|
- | - | |
| 05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $9,328 | $20,000 |
$6,510
121,660
kWh
|
$2,818
-
kW-mo/yr
|
- | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $26,710 | $73,600 |
$26,710
561,139
kWh
|
- | - | |
| 07 | 2.6231: Utilize controls to operate equipment only when needed | $12,202 | $20,000 |
$8,510
159,030
kWh
|
$3,692
-
kW-mo/yr
|
- | |
| 08 | 2.5113: Use direct flame impingement or infrared processing for chamber type heating | $63,868 | $350,000 | - | - |
$63,868
-
MMBtu
|
|
| TOTAL RECOMMENDED | $127,739 | $634,533 |
$55,035
1,115,524
kWh
|
$8,836
-
kW-mo/yr
|
$63,868
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $83,873 | $521,300 |
$17,187
345,945
kWh
|
$2,818
-
kW-mo/yr
|
$63,868
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs