Assessment Year | 2006 |
---|---|
Principal Product | Industrial Fabric for Conveyer Belts |
NAICS | 314999: All Other Miscellaneous Textile Product Mills |
SIC | 2299: Textile goods, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 200 |
Plant Area |
500,000
ft2
|
Annual Production | 21,000,000
lb
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $404,537 | 10,211,082 |
kWh
|
$0.040 |
Electricity Demand | $80,557 | 18,207 |
kW-mo/yr
|
$4.42 |
Electricity Fees | $67,169 | - |
|
- |
Natural Gas | $332,449 | 30,291 |
MMBtu
|
$10.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $103,907 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,299 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $8,981 | $1,333 |
$8,981
252,288
kWh
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $40,933 | $164,201 |
$30,883
664,148
kWh
|
$10,050
-
kW-mo/yr
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,177 | $9,625 |
$9,233
247,557
kWh
|
$1,944
-
kW-mo/yr
|
- | - | |
04 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $3,469 | $7,920 |
$3,469
97,445
kWh
|
- | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,652 | $500 |
$2,652
74,481
kWh
|
- | - | - | |
06 | 2.4224: Upgrade controls on compressors | $2,666 | $1,500 |
$2,666
74,880
kWh
|
- | - | - | |
07 | 2.2414: Use waste heat from hot flue gases to preheat | $32,042 | $15,000 | - | - | - |
$32,042
-
MMBtu
|
|
08 | 2.8112: Combine utility meters | $1,987 | - | - | - | $1,987 | - | |
TOTAL RECOMMENDED | $103,907 | $200,079 |
$57,884
1,410,799
kWh
|
$11,994
-
kW-mo/yr
|
$1,987 |
$32,042
-
MMBtu
|
||
TOTAL IMPLEMENTED | $14,299 | $3,333 |
$14,299
401,649
kWh
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs