Assessment Year | 2002 |
---|---|
Principal Product | Bearings |
NAICS |
n/a
|
SIC | 3562: Ball and Roller Bearings |
Sales Range | $50 M to 100M |
# of Employees | 460 |
Plant Area |
265,000
ft2
|
Annual Production | 100,000,000
pieces
|
Production Hrs. Annual | 6,900
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $542,970 | 24,652,800 |
kWh
|
$0.022 |
Electricity Demand | $606,107 | 3,845 |
kW-mo/yr
|
$157.64 |
Electricity Fees | $113,645 | - |
|
- |
Natural Gas | $326,438 | 63,520 |
MMBtu
|
$5.14 |
Fuel Oil #2 | $15,121 | 2,342 |
MMBtu
|
$6.46 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $242,959 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $34,601 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4224: Upgrade controls on compressors | $1,545 | - |
$1,545
70,086
kWh
|
- | - | - | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $33,056 | $2,500 |
$9,334
323,480
kWh
|
$9,722
-
kW-mo/yr
|
- | - | $9,000 | $5,000 | |
03 | 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air | $62,171 | $130,800 |
$24,782
1,124,417
kWh
|
$45,009
-
kW-mo/yr
|
$(-7,620.0)
-
MMBtu
|
- | - | - | |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,365 | - | - | - |
$1,365
-
MMBtu
|
- | - | - | |
05 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $3,122 | $1,000 |
$1,463
66,400
kWh
|
$2,659
-
kW-mo/yr
|
$(-1,000.0)
-
MMBtu
|
- | - | - | |
06 | 4.446: Automate finishing process | $130,680 | $10,300 | - | - | - | - | $130,680 | - | |
07 | 3.4151: Minimize water usage | $11,020 | $21,250 | - | - | - |
$11,020
-
Tgal
|
- | - | |
TOTAL RECOMMENDED | $242,959 | $165,850 |
$37,124
1,584,383
kWh
|
$57,390
-
kW-mo/yr
|
$(-7,255.0)
-
MMBtu
|
$11,020
-
Tgal
|
$139,680 | $5,000 | ||
TOTAL IMPLEMENTED | $34,601 | $2,500 |
$10,879
393,566
kWh
|
$9,722
-
kW-mo/yr
|
- | - | $9,000 | $5,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs