Assessment Year | 2002 |
---|---|
Principal Product | yellow pine lumber |
NAICS | 321113: Sawmills |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
400,000
ft2
|
Annual Production | 64,000,000
thousand feet
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $312,076 | 6,056,388 |
kWh
|
$0.052 |
Natural Gas | $671 | 61 |
MMBtu
|
$11.00 |
Wood | $88,266 | 250,720 |
MMBtu
|
$0.35 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $2,196,973 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Wood Savings | Water Disposal Savings | Administrative Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8112: Combine utility meters | $13,100 | $1,000 | - | - | - | $13,100 | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $45,343 | $49,000 |
$45,343
824,443
kWh
|
- | - | - | - | |
03 | 2.2693: Use waste heat steam for absorption refrigeration | $56,762 | $237,300 |
$56,762
293,083
kWh
|
- | - | - | - | |
04 | 2.1116: Improve combustion control capability | $22,495 | $2,500 | - |
$22,495
-
MMBtu
|
- | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,965 | $14,670 |
$6,965
139,215
kWh
|
- | - | - | - | |
06 | 2.4226: Use / purchase optimum sized compressor | $51,992 | $57,500 |
$1,918
34,584
kWh
|
- |
$50,074
-
Tgal
|
- | - | |
07 | 2.2511: Insulate bare equipment | $316 | $1,132 | - |
$316
-
MMBtu
|
- | - | - | |
08 | 4.446: Automate finishing process | $2,000,000 | $200,000 | - | - | - | - | $2,000,000 | |
TOTAL RECOMMENDED | $2,196,973 | $563,102 |
$110,988
1,291,325
kWh
|
$22,811
-
MMBtu
|
$50,074
-
Tgal
|
$13,100 | $2,000,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Wood Savings | Water Disposal Savings | Administrative Changes Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs