ITAC Assessment: GT0733
ITAC logo
ITAC Assessment: GT0733
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product yellow pine lumber
NAICS 321113: Sawmills
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 400,000
ft2
Annual Production 64,000,000
thousand feet
Production Hrs. Annual 2,340
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $312,076 6,056,388
kWh
Natural Gas $671 61
MMBtu
Wood $88,266 250,720
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $2,196,973 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Wood Savings Water Disposal Savings Administrative Changes Savings Primary Product Savings
01 2.8112: Combine utility meters $13,100 $1,000 - - - $13,100 -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $45,343 $49,000 $45,343
824,443
kWh
- - - -
03 2.2693: Use waste heat steam for absorption refrigeration $56,762 $237,300 $56,762
293,083
kWh
- - - -
04 2.1116: Improve combustion control capability $22,495 $2,500 - $22,495
-
MMBtu
- - -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $6,965 $14,670 $6,965
139,215
kWh
- - - -
06 2.4226: Use / purchase optimum sized compressor $51,992 $57,500 $1,918
34,584
kWh
- $50,074
-
Tgal
- -
07 2.2511: Insulate bare equipment $316 $1,132 - $316
-
MMBtu
- - -
08 4.446: Automate finishing process $2,000,000 $200,000 - - - - $2,000,000
TOTAL RECOMMENDED $2,196,973 $563,102 $110,988
1,291,325
kWh
$22,811
-
MMBtu
$50,074
-
Tgal
$13,100 $2,000,000
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Wood Savings Water Disposal Savings Administrative Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs