ITAC Assessment: GT0457
ITAC logo
ITAC Assessment: GT0457
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product METAL FURNITURE
NAICS
n/a
SIC 3429: Hardware, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area
n/a
Annual Production 11,000,000
lb
Production Hrs. Annual 1,960
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $54,521 691,970
kWh
Natural Gas $22,607 4,117
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,377 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,507 $6,820 $1,679
21,395
kWh
- $(-172.0)
02 2.6232: Install set-back timers $1,450 - $1,450
18,464
kWh
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,340 $800 $1,340
16,999
kWh
- -
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $11,540 - $25,546
311,547
kWh
$(-14,006.0)
-
MMBtu
-
05 2.7261: Install timers and/or thermostats $5,540 $3,900 - $5,540
-
MMBtu
-
TOTAL RECOMMENDED $21,377 $11,520 $30,015
368,405
kWh
$(-8,466.0)
-
MMBtu
$(-172.0)
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs