Assessment Year | 2016 |
---|---|
Principal Product | Plastic food containers |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
80,000
ft2
|
Annual Production | 25,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $108,659 | 3,714,640 |
kWh
|
$0.029 |
Electricity Demand | $47,988 | 6,471 |
kW-mo/yr
|
$7.42 |
Electricity Fees | $3,400 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $29,753 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,573 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $9,870 | $20 |
$7,880
143,280
kWh
|
$1,990
-
kW-mo/yr
|
- | |
02 | 2.6218: Turn off equipment when not in use | $8,000 | - |
$8,000
145,700
kWh
|
- | - | |
03 | 2.3212: Optimize plant power factor | $5,687 | $19,900 | - |
$5,687
-
kW-mo/yr
|
- | |
04 | 2.9131: Install hydrogen fuel cell | $3,180 | - |
$1,010
18,360
kWh
|
- | $2,170 | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,425 | $1,350 |
$1,425
25,900
kWh
|
- | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $940 | $200 |
$750
13,660
kWh
|
$190
-
kW-mo/yr
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $586 | $200 |
$130
2,505
kWh
|
$18
-
kW-mo/yr
|
$438 | |
08 | 2.7135: Install occupancy sensors | $65 | $60 |
$65
1,230
kWh
|
- | - | |
TOTAL RECOMMENDED | $29,753 | $21,730 |
$19,260
350,635
kWh
|
$7,885
-
kW-mo/yr
|
$2,608 | ||
TOTAL IMPLEMENTED | $18,573 | $21,730 |
$10,250
186,575
kWh
|
$7,885
-
kW-mo/yr
|
$438 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs