ITAC Assessment: GT0436
ITAC logo
ITAC Assessment: GT0436
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product BUILDING MARBLE
NAICS
n/a
SIC 3281: Cut Stone and Stone Products
Sales Range $5
M
to 10
M
# of Employees 72
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 2,040
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $220,399 2,584,115
kWh
Natural Gas $49,838 8,435
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $52,772 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $43,650 - $43,650
-
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $44 - $140
2,052
kWh
- $(-96.0)
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,488 $5,487 $1,488
21,688
kWh
- -
04 2.4133: Use most efficient type of electric motors $387 $4,645 $387
2,931
kWh
- -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,085 - $1,085
15,826
kWh
- -
06 2.4221: Install compressor air intakes in coolest locations $260 $300 $260
3,810
kWh
- -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,970 $2,400 $3,970
57,737
kWh
- -
08 2.1233: Analyze flue gas for proper air/fuel ratio $1,238 - - $738
-
MMBtu
$500
09 2.2136: Install / repair insulation on steam lines $310 $119 - $310
-
MMBtu
-
10 2.7261: Install timers and/or thermostats $340 $100 - $340
-
MMBtu
-
TOTAL RECOMMENDED $52,772 $13,051 $50,980
104,044
kWh
$1,388
-
MMBtu
$404
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs