ITAC Assessment: GT0411
ITAC logo
ITAC Assessment: GT0411
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product STAINLESS STEEL FRAMES
NAICS
n/a
SIC 3356: Rolling, Drawing, and Extruding of Nonferrous Metals, Except Copper and Aluminum
Sales Range $5
M
to 10
M
# of Employees 90
Plant Area
n/a
Annual Production 980,000
pieces
Production Hrs. Annual 2,805
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $37,431 461,899
kWh
Natural Gas $5,624 795
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,159 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,520

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.6232: Install set-back timers $3,510 - $3,510
43,376
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $393 $48 $393
4,982
kWh
03 2.6212: Turn off equipment during breaks, reduce operating time $914 - $914
11,137
kWh
04 2.4133: Use most efficient type of electric motors $533 $678 $533
6,448
kWh
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $639 - $639
7,913
kWh
06 2.4221: Install compressor air intakes in coolest locations $170 $450 $170
2,052
kWh
TOTAL RECOMMENDED $6,159 $1,176 $6,159
75,908
kWh
TOTAL IMPLEMENTED $5,520 $1,176 $5,520
67,995
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs