ITAC Assessment: GT0387
ITAC logo
ITAC Assessment: GT0387
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product COMMERCIAL PRINT
NAICS
n/a
SIC 2711: Newspapers: Publishing, or Publishing and Printing
Sales Range $5
M
to 10
M
# of Employees 85
Plant Area
n/a
Annual Production 5,000
ton
Production Hrs. Annual 4,160
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $34,144 526,084
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,536 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,495

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7447: Install vinyl strip / high speed / air curtain doors $645 $450 $645
10,844
kWh
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,942 $2,325 $2,942
44,842
kWh
03 2.7142: Utilize higher efficiency lamps and/or ballasts $769 $1,727 $769
11,723
kWh
04 2.2437: Recover waste heat from equipment $850 $1,200 $850
12,896
kWh
05 2.6232: Install set-back timers $330 $330 $330
4,982
kWh
TOTAL RECOMMENDED $5,536 $6,032 $5,536
85,287
kWh
TOTAL IMPLEMENTED $1,495 $1,650 $1,495
23,740
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs