ITAC Assessment: GT0122
ITAC logo
ITAC Assessment: GT0122
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product SILK SCREEN SIGNS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $500
k
to 1
M
# of Employees 22
Plant Area
n/a
Annual Production 5,000,000
pieces
Production Hrs. Annual 2,080
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $4,351 54,220
kWh
Natural Gas $4,190 993
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $2,627 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,627

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7261: Install timers and/or thermostats $1,550 $750 - $1,550
-
MMBtu
02 2.7447: Install vinyl strip / high speed / air curtain doors $732 $1,100 - $732
-
MMBtu
03 2.7142: Utilize higher efficiency lamps and/or ballasts $230 $51 $230
2,931
kWh
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $115 $35 $115
1,465
kWh
-
TOTAL RECOMMENDED $2,627 $1,936 $345
4,396
kWh
$2,282
-
MMBtu
TOTAL IMPLEMENTED $2,627 $1,936 $345
4,396
kWh
$2,282
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs