Assessment Year | 2013 |
---|---|
Principal Product | stainless steel gas springs |
NAICS | 333995: Fluid Power Cylinder and Actuator Manufacturing |
SIC | 3593: Fluid Power Cylinders and Actuators |
Sales Range | $1 M to 5M |
# of Employees | 13 |
Plant Area |
9,000
ft2
|
Annual Production | 100,000
pieces
|
Production Hrs. Annual | 2,423
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $5,109 | 64,415 |
kWh
|
$0.079 |
Electricity Demand | $4,130 | 372 |
kW-mo/yr
|
$11.10 |
Electricity Fees | $1,481 | - |
|
- |
LPG | $2,659 | 96 |
MMBtu
|
$27.70 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,977 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings |
---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $97 | - |
$57
727
kWh
|
$40
-
kW-mo/yr
|
- | |
02 | 2.2437: Recover waste heat from equipment | $1,340 | $132 | - | - |
$1,340
-
MMBtu
|
|
03 | 2.7233: Use properly designed and sized hvac equipment | $335 | $738 | - | - |
$335
-
MMBtu
|
|
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $155 | $655 | - |
$155
-
kW-mo/yr
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $50 | $238 |
$50
627
kWh
|
- | - | |
TOTAL RECOMMENDED | $1,977 | $1,763 |
$107
1,354
kWh
|
$195
-
kW-mo/yr
|
$1,675
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs