ITAC Assessment: SU0345
ITAC logo
ITAC Assessment: SU0345
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product stainless steel gas springs
NAICS 333995: Fluid Power Cylinder and Actuator Manufacturing
SIC 3593: Fluid Power Cylinders and Actuators
Sales Range $1
M
to 5
M
# of Employees 13
Plant Area 9,000
ft2
Annual Production 100,000
pieces
Production Hrs. Annual 2,423
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $5,109 64,415
kWh
Electricity Demand $4,130 372
kW-mo/yr
Electricity Fees $1,481 -
LPG $2,659 96
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,977 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings
01 2.7111: Reduce illumination to minimum necessary levels $97 - $57
727
kWh
$40
-
kW-mo/yr
-
02 2.2437: Recover waste heat from equipment $1,340 $132 - - $1,340
-
MMBtu
03 2.7233: Use properly designed and sized hvac equipment $335 $738 - - $335
-
MMBtu
04 2.3131: Reschedule plant operations or reduce load to avoid peaks $155 $655 - $155
-
kW-mo/yr
-
05 2.4221: Install compressor air intakes in coolest locations $50 $238 $50
627
kWh
- -
TOTAL RECOMMENDED $1,977 $1,763 $107
1,354
kWh
$195
-
kW-mo/yr
$1,675
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs