ITAC Assessment: GT0119
ITAC logo
ITAC Assessment: GT0119
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product MEN'S SUITS
NAICS
n/a
SIC 2311: Men's and Boys' Suits, Coats, and Overcoats
Sales Range $10
M
to 50
M
# of Employees 30
Plant Area
n/a
Annual Production 1,800,000
pieces
Production Hrs. Annual 2,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $9,217 213,072
kWh
Natural Gas $8,122 1,886
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,313 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $491

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7229: Air condition only space necessary $3,696 $700 - $3,696
-
MMBtu
02 2.7261: Install timers and/or thermostats $1,524 $2,000 - $1,524
-
MMBtu
03 2.7444: Close holes and openings in building such as broken windows $491 $224 - $491
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $372 $359 $372
8,499
kWh
-
05 2.7447: Install vinyl strip / high speed / air curtain doors $230 $900 - $230
-
MMBtu
TOTAL RECOMMENDED $6,313 $4,183 $372
8,499
kWh
$5,941
-
MMBtu
TOTAL IMPLEMENTED $491 $224 - $491
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs