Assessment Year | 1999 |
---|---|
Principal Product | Valves and Regulators |
NAICS |
n/a
|
SIC | 3491: Industrial Valves |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
41,000
ft2
|
Annual Production | 26,000
pieces
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $99,992 | 2,419,695 |
kWh
|
$0.041 |
Electricity Demand | $38,094 | 5,688 |
kW-mo/yr
|
$6.70 |
Electricity Fees | $336 | - |
|
- |
Natural Gas | $6,289 | 1,254 |
MMBtu
|
$5.02 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,006 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $4,412 | $3,358 |
$2,313
56,565
kWh
|
- |
$2,099
-
MMBtu
|
- | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $301 | $343 |
$205
4,982
kWh
|
$96
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.2437: Recover waste heat from equipment | $635 | $1,156 |
$635
28,722
kWh
|
- | - | - | - | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,400 | $4,365 |
$1,266
30,774
kWh
|
$796
-
kW-mo/yr
|
$(-662.0)
-
MMBtu
|
- | - | - | |
05 | 3.6124: Burn waste oil for heat | $857 | $1,695 |
$174
10,258
kWh
|
- | - | - |
$683
-
gal
|
- | |
06 | 3.4156: Use flow control valves on equipment to optimize water use | $1,498 | $2,832 | - | - | - |
$1,498
-
Tgal
|
- | - | |
07 | 4.611: Begin a practice of predictive / preventative maintenance | $903 | - | - | - | - | - | - | $903 | |
TOTAL RECOMMENDED | $10,006 | $13,749 |
$4,593
131,301
kWh
|
$892
-
kW-mo/yr
|
$1,437
-
MMBtu
|
$1,498
-
Tgal
|
$683
-
gal
|
$903 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs