Assessment Year | 2025 |
---|---|
Principal Product | Water Filtration, Treatment Systems |
NAICS | 333318: Other Commercial and Service Industry Machinery Manufacturing |
SIC | 3589: Service Industry Machinery, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 200 |
Plant Area |
300,000
ft2
|
Annual Production | 280,000
units
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $784,272 | 12,736,800 |
kWh
|
$0.062 | |
Electricity Demand | $387,399 | 26,946 |
kW-mo/yr
|
$14.38 | |
Natural Gas | $12,013 | 1,160 |
MMBtu
|
$10.36 | |
Waste Disposal Costs | |||||
Water Usage | $19,595 | 4,188 |
Tgal
|
$4.68 | |
TOTAL YEARLY COSTS | $1,203,279 | ||||
RECOMMENDED SAVINGS* | $298,353 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $1,878 | $2,514 |
$1,675
27,015
kWh
|
$203
-
kW-mo/yr
|
|
02 | 2.7232: Replace existing hvac unit with high efficiency model | $3,035 | $40,500 |
$3,035
48,955
kWh
|
- | |
03 | 2.6127: Maintain air filters by cleaning or replacement | $22,444 | $2,454 |
$22,444
362,004
kWh
|
- | |
04 | 2.9114: Use solar heat to make electricty | $270,995 | $2,128,000 |
$205,423
3,313,268
kWh
|
$65,573
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $298,353 | $2,173,467 |
$232,577
3,751,242
kWh
|
$65,776
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs