Assessment Year | 1999 |
---|---|
Principal Product | Precision measuring tools and optical comparators |
NAICS |
n/a
|
SIC | 3545: Cutting Tools, Machine Tool Accessories, and Machinists' Precision Measuring Devices |
Sales Range | $5 M to 10M |
# of Employees | 110 |
Plant Area |
35,000
ft2
|
Annual Production | 64,400
pieces
|
Production Hrs. Annual | 4,810
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $39,096 | 1,056,858 |
kWh
|
$0.037 |
Electricity Demand | $13,822 | 4,704 |
kW-mo/yr
|
$2.94 |
Electricity Fees | $1,748 | - |
|
- |
Natural Gas | $19,591 | 5,648 |
MMBtu
|
$3.47 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $21,460 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $21,460 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $1,047 | $1,960 | - | - | $1,047 | - | - | - | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,330 | $29,424 |
$6,715
181,712
kWh
|
$1,615
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
03 | 2.2511: Insulate bare equipment | $1,921 | $1,137 |
$1,042
28,136
kWh
|
- | - |
$879
-
MMBtu
|
- | - | - | - | - | |
04 | 2.7261: Install timers and/or thermostats | $2,815 | $2,459 | - | - | - |
$2,815
-
MMBtu
|
- | - | - | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $123 | $91 |
$81
2,345
kWh
|
$42
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
06 | 2.4321: Upgrade obsolete equipment | $3,713 | $7,827 | - | - | - | - |
$1,591
-
Tgal
|
- | - | - |
$2,122
-
Tgal
|
|
07 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $924 | $1,000 | - | - | - | - | - | - | - | $924 | - | |
08 | 3.6124: Burn waste oil for heat | $1,552 | $1,695 | - | - | - |
$187
-
MMBtu
|
- |
$1,365
-
gal
|
- | - | - | |
09 | 4.515: Install shelves / racks to utilize unused space | $1,035 | $120 | - | - | - | - | - | - | $1,035 | - | - | |
TOTAL RECOMMENDED | $21,460 | $45,713 |
$7,838
212,193
kWh
|
$1,657
-
kW-mo/yr
|
$1,047 |
$3,881
-
MMBtu
|
$1,591
-
Tgal
|
$1,365
-
gal
|
$1,035 | $924 |
$2,122
-
Tgal
|
||
TOTAL IMPLEMENTED | $21,460 | $45,713 |
$7,838
212,193
kWh
|
$1,657
-
kW-mo/yr
|
$1,047 |
$3,881
-
MMBtu
|
$1,591
-
Tgal
|
$1,365
-
gal
|
$1,035 | $924 |
$2,122
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs