| Assessment Year | 1999 |
|---|---|
| Principal Product | Custom Commercial Cabinetry |
| NAICS |
n/a
|
| SIC | 2541: Wood Office and Store Fixtures, Partitions, Shelving, and Lockers |
| Sales Range | $10 M to 50M |
| # of Employees | 92 |
| Plant Area |
112,000
ft2
|
| Annual Production | 67
thousand feet
|
| Production Hrs. Annual | 5,512
hrs
|
| Location (State) | Minnesota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $102,226 | 1,683,177 |
kWh
|
$0.061 |
| Electricity Demand | $39,987 | 6,012 |
kW-mo/yr
|
$6.65 |
| Electricity Fees | $4,883 | - |
|
- |
| Natural Gas | $15,409 | 2,896 |
MMBtu
|
$5.32 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,250 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $17,910 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $865 | $324 |
$865
25,498
kWh
|
- | - | - | - | - | - | |
| 02 | 2.2437: Recover waste heat from equipment | $863 | $1,010 | - | - |
$863
-
MMBtu
|
- | - | - | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $221 | $375 |
$156
4,689
kWh
|
$65
-
kW-mo/yr
|
- | - | - | - | - | |
| 04 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $13,380 | $3,000 | - | - | - | - | - | $13,380 | - | |
| 05 | 3.4151: Minimize water usage | $340 | $230 | - | - | - | - | - | - |
$340
-
Tgal
|
|
| 06 | 4.446: Automate finishing process | $1,925 | $4,900 | - | - | - | $1,925 | - | - | - | |
| 07 | 4.821: Pay bills on time to avoid late fees | $656 | - | - | - | - | - | $656 | - | - | |
| TOTAL RECOMMENDED | $18,250 | $9,839 |
$1,021
30,187
kWh
|
$65
-
kW-mo/yr
|
$863
-
MMBtu
|
$1,925 | $656 | $13,380 |
$340
-
Tgal
|
||
| TOTAL IMPLEMENTED | $17,910 | $9,609 |
$1,021
30,187
kWh
|
$65
-
kW-mo/yr
|
$863
-
MMBtu
|
$1,925 | $656 | $13,380 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs