Assessment Year | 1997 |
---|---|
Principal Product | Aquatic Sports Equipment |
NAICS |
n/a
|
SIC | 3949: Sporting and Athletic Goods, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
160,000
ft2
|
Annual Production | 1,100,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $54,564 | 1,047,480 |
kWh
|
$0.052 |
Electricity Demand | $22,053 | 3,764 |
kW-mo/yr
|
$5.86 |
Electricity Fees | $4,935 | - |
|
- |
Natural Gas | $63,115 | 15,097 |
MMBtu
|
$4.18 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $196,162 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $189,580 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,363 | $1,118 |
$3,301
63,306
kWh
|
$62
-
kW-mo/yr
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,909 | $800 |
$4,909
91,442
kWh
|
- | - | - | - | |
03 | 2.6218: Turn off equipment when not in use | $205 | $360 |
$205
3,810
kWh
|
- | - | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $297 | $453 |
$242
4,689
kWh
|
$55
-
kW-mo/yr
|
- | - | - | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $4,337 | $1,495 | - | - |
$4,337
-
MMBtu
|
- | - | |
06 | 2.2414: Use waste heat from hot flue gases to preheat | $2,717 | $3,000 | - | - |
$2,717
-
MMBtu
|
- | - | |
07 | 3.6192: Use a less expensive method of waste removal | $12,812 | - | - | - | - |
$12,812
-
lb
|
- | |
08 | 4.122: Develop standard procedures to improve internal yields | $167,522 | - | - | - | - |
$1,294
-
lb
|
$166,228 | |
TOTAL RECOMMENDED | $196,162 | $7,226 |
$8,657
163,247
kWh
|
$117
-
kW-mo/yr
|
$7,054
-
MMBtu
|
$14,106
-
lb
|
$166,228 | ||
TOTAL IMPLEMENTED | $189,580 | $2,295 |
$4,909
91,442
kWh
|
- |
$4,337
-
MMBtu
|
$14,106
-
lb
|
$166,228 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs