ITAC Assessment: UW0035
ITAC logo
ITAC Assessment: UW0035
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Cheese, Dairy Products
NAICS 311513: Cheese Manufacturing
SIC 2022: Natural, Processed, and Imitation Cheese
Sales Range $100
M
to 500
M
# of Employees 140
Plant Area 40,000
ft2
Annual Production 182,000,000
lb
Production Hrs. Annual 7,300
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,255,560 31,541,760
kWh
Electricity Demand $217,320 18,110
kW-mo/yr
Natural Gas $2,977,877 420,165
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $114,175 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $49,758

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2414: Use waste heat from hot flue gases to preheat $58,000 - - - $58,000
-
MMBtu
02 2.1116: Improve combustion control capability $28,000 $77,000 - - $28,000
-
MMBtu
03 2.4133: Use most efficient type of electric motors $18,058 $1 $15,880
399,496
kWh
$2,178
-
kW-mo/yr
-
04 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $6,417 - $5,642
142,109
kWh
$775
-
kW-mo/yr
-
05 2.2511: Insulate bare equipment $3,700 $2,000 - - $3,700
-
MMBtu
TOTAL RECOMMENDED $114,175 $79,001 $21,522
541,605
kWh
$2,953
-
kW-mo/yr
$89,700
-
MMBtu
TOTAL IMPLEMENTED $49,758 $79,001 $15,880
399,496
kWh
$2,178
-
kW-mo/yr
$31,700
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs